Lithium Americas Corp. · NYSE · Metal Mining · CIK 1966983 · All filings on SEC.gov

Everything below is quoted or computed from Lithium Americas Corp.'s public SEC filings. It is not a recommendation to buy or sell. Automated comparisons can contain errors; confirm with the original filing.

At a glance

31 / 39risk-factor paragraphs added / removed in latest 10-K
5new risk-factor headings
0Form 4 filings reporting open-market purchases (last 180 days)
1Form 4 filings reporting open-market sales (last 180 days)

Jump to: Annual report (10-K) · Quarterly report (10-Q) · Insider transactions · 13F holders

What changed in the latest 10-K

Comparing 10-K filed 2026-03-19 (period ending 2025-12-31) with 10-K filed 2025-03-28 (period ending 2024-12-31).

Risk Factors (10-K Item 1A)

31new paragraphs
39removed paragraphs
47reworded paragraphs
15,367 → 14,854words in section

New heading “Actual capital costs, schedules, production levels, operating costs, economic returns, and other estimates may differ from expectations which could which could materially and adversely affect cash flows, profitability, and increase funding requirements”

New heading “GM and the DOE have rights that may affect other security holders and the Company's actions with respect to the development of Thacker Pass through their respective investor and creditor rights, rights as a JV Partner (in the case of GM) and other rights”

New heading “The Company’s growing dependence on complex digital systems and third-party technologies increases exposure to evolving cybersecurity threats that could disrupt operations, result in financial, legal, and reputational harm, and require ongoing investment and governance oversight to mitigate”

New heading “Certain events could cause the Arrangement to lose its intended tax-free status, leading to significant U.S. federal income tax liabilities for U.S. Shareholders”

New heading “The Company’s financial performance depends in part on the continued availability of tax credits relating to the production of critical minerals, which if not available, could limit the Company’s revenue once commercial production is reached and harm the Company’s business and financial condition”

Removed heading “Risk Relating to Resource Development”

Removed heading “There can be no assurances when or if the Orion Investment will be completed”

Removed heading “The expected capital and operating costs for Thacker Pass are based on various assumptions that may prove inaccurate, and any discrepancies could lead to increased costs and the need for additional funding to complete Phase 1 and meet working capital requirements”

Removed heading “Risks Relating to Lithium Production and Operations”

Removed heading “Failure to achieve production estimates for Thacker Pass, due to inaccuracies in assumptions or lower quality ore, could materially and adversely affect cash flows and profitability”

Removed heading “Actual costs and production may vary due to factors such as resource availability and inflation”

Removed heading “Risks Related to the Company’s Business and Securities”

Removed heading “GM has significant influence over Thacker Pass’s development due to investor rights, its rights as a JV Partner and board representation at both the Company and Lithium Nevada Ventures, which may affect other securityholders and the Company’s actions, including the determination to make a FID in respect of Phase 1 of Thacker Pass”

Removed heading “Upon conversion of the Orion Note, if issued, Orion may hold a substantial equity position in LAC’s business and may thereafter exercise influence over the Company”

Removed heading “Financing through capital markets could dilute shareholders’ interests and impose restrictions”

Removed heading “Increased reliance on digital technologies and new information systems to support the growing business could increase costs and cybersecurity related threats”

Removed heading “Loss of FPI status requires increased regulatory reporting requirements and associated costs”

Removed heading “Shareholders may face significant tax liabilities, impacting the intended tax-free status of the Common Shares received pursuant to the Arrangement.”

Largest changes (selected automatically by length and topic keywords; quoted verbatim, no commentary)

New text topics: tariff, middle east, supply chain, inflation
“Actual capital costs, schedules, production levels, operating costs, and economic returns may vary significantly from current assumptions and estimates due to factors such as the availability of labor, equipment, materials and other resources; inflationary pressure from higher energy and transportation costs, supply chain shortages, including as a result of conflicts in the Middle East and other international events; labor costs and productivity; labor shortages or strikes; construction and operating difficulties; cost overruns; revisions to construction or operating plans; …”
see in full comparison
Removed text topics: fine, cybersecurity incident, breach, ransomware
“Threats to information technology (“IT”) systems associated with cybersecurity risks and cyber incidents or attacks continue to grow and evolve in terms of severity and sophistication, particularly as a result of remote work. These threats include malicious software, phishing, credential theft, surveillance, social engineering, ransomware and other electronic security breaches, any of which could compromise the Company’s business, financial and operational systems. …”
see in full comparison
Removed text topics: tariff, supply chain, inflation, strike
“Feasibility reports and other mining studies, including the Reports, are inherently subject to uncertainties. Capital costs, operating costs, production and economic returns, and other estimates may differ significantly from those anticipated by the Company's current estimates, and there can be no assurance that the Company's actual capital, operating and other costs will not be higher than currently anticipated. …”
see in full comparison
Removed text topics: penalt, cybersecurity incident, breach, regulation
“Additionally, while the Company implements commercially reasonable security controls, such as detection systems, regular assessments, employee training and an incident response plan, these measures cannot guarantee protection against cybersecurity threats. As threats become more sophisticated, the risk of breaches or disruptions remains, and the Company may need to invest additional resources to enhance its defenses or address vulnerabilities. Although the Company has not experienced significant losses from cybersecurity incidents to date, no security system offers complete protection. …”
see in full comparison
New text topics: tariff, china, supply chain, labor
“The Company's business requires access to steel and other raw materials for use in the construction of Thacker Pass. Much equipment and construction material has been sourced from Canada, China, India, UAE, Turkey and the European Union, and may be subject to tariffs. The Company has been working toward limiting the effect of any potential tariffs on its construction supply chain, with approximately 75% of the total capital project cost structure related to labor, contractors and other services not expected to be directly affected by any potential tariffs. …”
see in full comparison
New text topics: tariff, supply chain, inflation, competition
“In addition, the Company expects risks relating to market conditions including but not limited to potential variability in demand for lithium products and competition in the market by various producers. The strength of market demand for lithium product end-uses cannot be assured. Other developers and producers of lithium are currently active in the production and exploration of lithium resources and could impact the availability and pricing of lithium. …”
see in full comparison
Full comparison: every changed paragraph (117)

Green = added, red = removed. Unchanged paragraphs, 2 paragraphs where only numbers/dates changed, and tables are not shown. Read the complete text in the original filing.

Reworded

The following are risk factors that the Company’s management believes are applicable to its business and the industry in which it operates. The risk factors set out below are not exhaustive and do not include risks the Company deems to be immaterial. If any of the events, risks or uncertainties described below actually occur, it or they may have a material adverse effect on the Company’s business, financial condition, operating results, or future prospects (including with respect to the price of the Company’s Common Shares). These risk factors are not necessarily presented in the order of importance or probability of occurrence.

Removed

Risk Relating to Resource Development

Reworded

Commercial viability of the Thacker Pass Project depends on numerous uncontrollable factorsfactors, suchincluding, aspermitting, permittingfinancing and financingdelays, that could negatively affect business and financial conditions

Reworded

There are many factors that could impact the development of Thacker Pass, including permitting, terms and availability of financing, including with respect to the closing of the Orion Investment, cost overruns, litigation or administrative appeals concerning the project, delays in development, and regulatory changes, among other factors. Thacker Pass is also subject to the development and operational risks described elsewhere in this Form 10-K. Accordingly, there can be no assurance that the Company will complete development of Thacker Pass as currently contemplated, or at all. If the Company is unable to developcomplete the development of Thacker Pass into a commercial operating mine, its business and financial condition would be materially adversely affected.

Reworded

The Company’s ability to continue to draw on the DOE Loan is contingent on meeting specific conditions and covenants, and failure to do so could lead to loan termination or other significant adverse effects

Added

On October 7, 2025, the Company entered into an OWCA by and among Lithium Nevada LLC (the “Borrower”), 1339480 B.C. Ltd. (the “B.C. Corp”), LAC US Corp. (the “LAC JV Member”), Lithium Nevada Venture (the “LAC-GM Joint Venture”), Lithium Nevada Projects LLC (the “Direct Parent”), Citibank, N.A. (the “Collateral Agent”) and the DOE, which became effective October 10, 2025. The OWCA provides for specified waivers, consents and amendments among the parties and, upon effectiveness, resulted in the satisfaction of all conditions to the first advance request under the DOE Loan being satisfied. The Company received its first advance of $435 million under the DOE Loan on October 20, 2025 and its second advance of $432 million on February 24, 2026.

Reworded

The Company’s ability to continue to draw down on the DOE Loan and to utilize such funds towards the construction and development of Phase 1 of Thacker Pass is dependent on the satisfaction of the set of conditions set out in the DOE Loan documents,documents includingcustomary for financings of a similar nature by the announcingU.S. ofGovernment FID,or whichother conditionspublic maylending be amended pursuant to the terms of the DOE Loan documents.institutions. There can be no assurance as to the satisfaction of these conditions or as to the outcome of any amended requirements, if any.conditions.

Reworded

The terms of the DOE Loan agreement also contain a number of significant restrictions and covenants that limit the Company’s ability under the DOE Loan agreement to, among other things: operate business outside of the ordinary course and enter into certain material contracts relating to the Thacker Pass Project without the prior consent of the DOE; incur liens and indebtedness or provide guarantees in respect of obligations of any other person; make loans and other investments and certain capital expenditures; issue equity securities for the Company’s subsidiaries; engage in mergers, consolidations and asset dispositions; and engage in affiliate transactions.

Removed

On January 20, 2025, President Trump signed an Executive Order which paused the disbursement of funds appropriated through the Inflation Reduction Act or the Infrastructure Investment and Jobs Act. The pause provides for a review of the processes, policies and issuances of various grants, loans, contracts or financial disbursements of appropriated funds. The Company’s DOE Loan is closed and will be funded by the Federal Financing Bank. However, any impact on the Company’s ability to amend the DOE Loan as a result of this Executive Order could adversely and materially impact its business to include increased costs, timeline delays and its ability to proceed with the development and construction of Phase I.

Removed

There can be no assurances when or if the Orion Investment will be completed

Removed

Although the Company expects to complete the Orion Investment early in the second quarter of 2025, there can be no assurances as to the exact timing of the closing of the Orion Investment or whether the Orion Investment will be completed at all. The closing of the Orion Investment is subject to numerous conditions, including announcement of FID by the JV Partners, and there can be no assurance that the conditions required to complete the Orion Investment, some of which are beyond our control, will be satisfied or waived on the anticipated schedule, or at all.

Reworded

Although the Company has obtained all key environmental permits for Thacker Pass for an initial stage of construction, there can be no certainty that current permits will be maintained, any permitting changes (such as changes to the mine plan or increases to planned capacity) will be approved, or additional local, state or federal permits or approvals required to carry out development and production at Thacker Pass will be obtained, projected timelines for permitting decisions to be made will be met, or the projected costs of permitting will be accurate.

Reworded

In addition, there is the risk that existing permits will be subject to challenges of regulatory administrative processes, and similar litigation and appeal processes. Litigation and regulatory review processes can result in lengthy delays, with uncertain outcomes. In the U.S., changes in the presidential administration may result in the suspension, revocation, or modification of certain regulations that the Company is subject to, thereby creating additional uncertainty. For example, Presidentthere Trump’shave been several recent signingdevelopments regarding the NEPA regulatory regime. Following an Executive Order of variousPresident ExecutiveTrump, Ordersthe White House Council on JanuaryEnvironmental 20,Quality 2025(“CEQ”) resultedreleased an interim final rule rescinding its regulations implementing NEPA. Federal agencies have begun the process of preparing their own new or updated NEPA-implementing rules or guidelines, with the first batch of updates released in July 2025. In May 2025, the temporarySupreme suspensionCourt ofissued agencyan approvalsopinion ofin someSeven projectsCounty Infrastructure Coalition v. Eagle County emphasizing the “substantial judicial deference” that courts must grant agencies when considering NEPA challenges. In September 2025, the CEQ issued new guidance to federal agencies implementing NEPA and forecastencouraging upcomingthem to limit their NEPA reviews, rely more heavily on sponsor-prepared documents, and streamline the NEPA process. A future administration may similarly implement changes in thehow regulatoryagencies frameworkcomply for federal environmental reviews underwith NEPA, which may result in permitting delays and additional uncertainty, as the process for agencies to update their NEPA regulations may be time-intensive, result in additional changes to the process that the Company does not anticipate, and result in increased litigation. Such issues as these could impact the expected development timelines of Thacker Pass and consequently have a material adverse effect on the Company's prospects and business.

Added

Actual capital costs, schedules, production levels, operating costs, economic returns, and other estimates may differ from expectations which could which could materially and adversely affect cash flows, profitability, and increase funding requirements

Added

Feasibility reports, this Form 10-K, and other mining studies, including the Reports, contain exploration, development and operations estimates relating to future capital costs, schedules, production levels, operating costs, and economic returns. These estimates are inherently uncertain and depend on numerous assumptions, including the accuracy of mineral reserve and resource estimates; assumptions regarding ore grades, ore quality and recovery rates; metallurgical characteristics; ground and physical conditions; construction and operating performance; the estimated rates and costs of mining, processing and chemical plant operations; and changes that impact the financial model considered following the effective date of the Reports. The Company expects to start a definitive capital cost estimate in the first half of 2026.

Added

Actual capital costs, schedules, production levels, operating costs, and economic returns may vary significantly from current assumptions and estimates due to factors such as the availability of labor, equipment, materials and other resources; inflationary pressure from higher energy and transportation costs, supply chain shortages, including as a result of conflicts in the Middle East and other international events; labor costs and productivity; labor shortages or strikes; construction and operating difficulties; cost overruns; revisions to construction or operating plans; lower than expected realized lithium prices; risks and hazards associated with construction, mineral production and chemical plant operations; natural events such as floods, fires, droughts or water shortages; and broader macroeconomic factors, including tariffs, interest rates and currency exchange rates. Many of these factors are beyond the Company's control.

Added

Although the Company currently expects that funding from the DOE Loan, and existing cash and cash equivalents will fully fund the remaining capital expenditures for Phase 1 of Thacker Pass and related working capital needs through expected initial production, these estimates may prove inaccurate. As a result of the foregoing uncertainties or other unforeseen factors, additional capital or working capital may be required to complete Phase 1 or sustain operations. Any material deviations from estimated capital or operating costs, schedules, production levels, ore grades, recovery rates or economic assumptions could have a material adverse effect on the Company’s business, financial condition, cash flows, results of operations, profitability, prospects and its ability to service indebtedness.

Removed

The expected capital and operating costs for Thacker Pass are based on various assumptions that may prove inaccurate, and any discrepancies could lead to increased costs and the need for additional funding to complete Phase 1 and meet working capital requirements

Removed

The expected capital and operating costs for Thacker Pass are based on the interpretation of geological and metallurgical data, feasibility studies, economic factors and other factors that may prove to be inaccurate. New tariffs imposed on certain metals used in the development of the Project could lead to an increase in commodity prices, causing construction to be delayed or to require greater capital investment. Therefore, the Reports may prove to be unreliable if the assumptions or estimates do not reflect actual facts and events. The following events, among other events and uncertainties described in the Reports, could affect the ultimate accuracy of such estimates: uncertainties in the interpreted geological data based on the representativeness of drill holes, in particular, unrecognized faults or basaltic units that could require changes to the mine plan or increased mine dilution or mine losses; unrecognized geotechnical conditions; unanticipated changes to the process flowsheet; increase in capital costs for any reason; and adverse weather conditions that could reduce mine equipment performance or require project-design changes.

Removed

As described elsewhere throughout this Form 10-K, the funding from the DOE Loan, the US$430 million of direct cash funding to the JV from GM expected as part of the JV Transaction, the Company’s existing cash and cash equivalents and the net proceeds expected from the initial closing of the Orion Investment are collectively expected to result in the estimated remaining capital expenditures for construction of Phase 1 of Thacker Pass and the estimated working capital requirements to fund the Company’s activities from the start of 2025 through expected initial production being fully funded. For the reasons set forth above and due to other factors, estimates relating to the cost of construction of Phase 1 and estimates relating to working capital requirements for such period may prove to be inaccurate, and currently unforeseen incremental funding may be required to complete Phase 1 in full and/or to fund such working capital requirements.

Reworded

The Company is and will continue to be subject to all risks inherent with establishing new mining and chemical processing operations including: the time and costs of construction of mining and processing facilities and related infrastructure; the availability and costs of skilled labor and mining equipment and supplies; the need to obtain and maintain necessary environmental and other governmental approvals, licenses and permits, and the timing of their issuance; the availability of funds to finance construction and development activities; potential opposition from non-governmental organizations, indigenous peoples, environmental groups or local groups which may delay or prevent development activities; and potential increases in construction and operating costs due to various factors, including the imposition of new tariffs by the Trump administration, that could lead to changes in the costs of fuel, power, labor, contractors, materials, supplies and equipment.

Reworded

More specifically, as a result of increased concerns around global supply chains, the lithium industry has become subject to increasing political involvement, including in the United States and Canada. This reflects thelithium’s critical role of lithium as an input in the development offor batteries forused the burgeoning transition toin electric vehicles inand theenergy automotivestorage industry,systems, combined with worldwideglobal supply constraints for lithium production and geopolitical tensions.tensions affecting lithium production. Political involvement appears to be evolving into a form of industrial policy by governments, including in Canada and the United States, to encourage the development of domestic supply through tax incentives and low-interest loans to domestic and other politically aligned actors, as well as by those governments undertaking steps to discourage the involvement of participants from non-politically aligned countries such as by tariffs and restrictions on ownership, influence and investment. These factors are of particular relevance to the Company, with its Canadian incorporation, U.S.-based Thacker Pass and predominant connection to Canada and the United States through its stock exchange listings, shareholder base and board and management composition. This evolving industrial policy may benefit the Company through the prospect of tax incentives and project financing. For example, on January 20, 2025, President Trump signed a sweeping energy-related Executive Order which directed various heads of agencies to identify and revise or rescind any actions imposing undue burdens on domestic mining and processing of non-fuel minerals. Various agencies have since taken action to rescind or otherwise modify existing regulatory requirements. However, the Company cannot predict what impacts this order or any subsequent regulatory actions may have on its operations, and there remains potential for delays in state approvals, permits and licenses notwithstanding thisthese order.actions. Moreover, notwithstanding such changes, there is the continued risk that policy approaches may shift over time, reducing or eliminating access to such benefits in the future. Increased government involvement may also present limitations on the extent to which the Company may undertake business operations with non-politically aligned parties, including limitations on ownership. The Company has and intends to continue to fully comply with legislation and policies in all jurisdictions where it operates. At this time, the Company cannot predict if any of these steps will result in a substantive adverse change to its business or operations, or the intended geographic focus of its business.

Reworded

There is also currently significant uncertainty about the future relationship between the United States and various other countries, including changes arising as a result of the newcurrent administration, with respect to trade policies, treaties, tariffs, taxes and other limitations on cross-border operations. Changes in tariffs, trade barriers, price and exchange controls and other regulatory requirements could have an adverse effect on the Company’s business, prospects, financial condition and operating results, the extent of which cannot be predicted with certainty at this time.

Removed

In 2025, the United States proposed to impose and enact tariffs on certain items. Potential new tariffs that could be imposed on certain metals used in development on the Project could cause input prices to increase, cause construction to be delayed or require greater capital investment. There have been ongoing discussions and activities regarding changes to other United States’ trade policies and treaties. In response, a number of countries, including Canada, Mexico, and China have implemented or threatened to implement tariffs on United States goods or to take other measures in response to these United States actions. These developments could have a material adverse effect on global economic conditions and the stability of global financial markets, and they may significantly reduce global trade and, in particular, trade between each of Canada, the United States and other affected countries. Any of these factors could depress economic activity and have a material adverse effect on the Company’s business, financial condition and results of operations. These actions are a recent development and are subject to a number of uncertainties as they are implemented, including future adjustments and changes in the countries excluded from such tariffs. The ultimate reaction of other countries, and businesses in those countries, and the impact of these tariffs or other actions on the United States and Canada, the global economy, the demand for lithium and market price of lithium-based products, the Company’s business, operations or financial results therefrom, cannot be predicted at this time, nor can the Company predict the impact of any other developments with respect to global trade and related disputes. In addition, to the extent the Company’s activities source products, materials, equipment, and services from countries other than the United States, the price and availability of those products, materials, equipment, and services could be impacted by the recently imposed tariffs and/or other penalties. Such cost increases could delay or cause the Company to incur significant expenditures that are not provided for in the Company’s budgets, which could have a material adverse effect on the Company’s business, operations, and the financial results therefrom, including the timing and development of Thacker Pass.

Reworded

Changes in government laws and regulations, including those related to taxation, environmental compliance and permitting, may affect development and operations

Reworded

Changes to government laws and regulations may affect the development of Thacker Pass. Such changes could include laws relating to taxation, royalties, restrictions on production, export controls, tariffs, environmental, biodiversity and ecological compliance, mine development and operations, labor, mine safety, permitting and numerous other aspects of the Company’s business. Many of these changes may result from a change in presidential administrations; forFor example, President Trump in a suite of Executive Orders, has directed the pause, modification or revocation of various previous Executive Orders and regulations that directly and indirectly affect the development of Thacker Pass, to include upcoming revisions to the approachPass; federal agencies takesubsequently inrevised their approach to complying with environmental reviews and eliminationfederal ofagencies have taken steps to eliminate an electric vehicle “mandate” which may adversely affect demand for lithium.

Added

The Company's business and results of operations may be adversely affected by uncertainty and changes in U.S. trade policies, including tariffs, trade agreements or other trade restrictions imposed by the U.S. or other governments. Although the Supreme Court recently invalidated the tariffs imposed by the administration under the International Emergency Economic Powers Act (“IEEPA”), certain tariff rates and obligations established through trade agreements that were negotiated during active IEEPA tariffs remain in effect, and the administration announced additional tariffs pursuant to the Trade Act of 1974. The administration has indicated that it will continue seeking to implement tariffs through other statutory authorities as well. These actions are unprecedented and have caused substantial uncertainty and volatility in financial markets, including uncertainty about the availability of refunds for prior tariffs and the imposition of new tariffs to replace those imposed under IEEPA. It remains unclear to what extent, upon which countries, and upon which terms, tariffs may be levied. Because of this, uncertainty remains elevated, as the administration continues to adjust tariff structures and consider additional country specific tariffs.

Added

The Company's business requires access to steel and other raw materials for use in the construction of Thacker Pass. Much equipment and construction material has been sourced from Canada, China, India, UAE, Turkey and the European Union, and may be subject to tariffs. The Company has been working toward limiting the effect of any potential tariffs on its construction supply chain, with approximately 75% of the total capital project cost structure related to labor, contractors and other services not expected to be directly affected by any potential tariffs. Any imposition of or increase in tariffs on imports of steel or other raw materials, as well as corresponding price increases for such materials available domestically, could increase the Company's construction costs and negatively impact the Company's ability to complete the construction of Thacker Pass on budget. Higher materials costs could also diminish the Company's ability to develop new projects at acceptable returns, particularly during times of economic uncertainty, and limit the Company's ability to pursue growth opportunities that may otherwise be available to the Company.

Added

The imposition of further tariffs by the U.S. on a broader range of imports, or further retaliatory trade measures taken in response to additional tariffs, could increase costs in the Company's supply chain or reduce demand for the Company's or the Company's customers’ products, either of which could adversely affect the Company's results of operations. To the extent any such tariffs remain in place for a sustained period of time, or in the event of a global or domestic recession resulting therefrom, the Company's customers could decide to delay currently planned growth projects or forego them entirely, each of which could result in decreased demand for the Company's products and adversely affect the Company's results of operations and financial condition.

Added

Changes in tariffs and trade restrictions can be announced with little or no advance notice. The adoption and expansion of tariffs or other trade restrictions, increasing trade tensions, or other changes in governmental policies related to taxes, tariffs, trade agreements or policies, are difficult to predict, which makes attendant risks difficult to anticipate and mitigate. The ultimate impact of these trade measures on the Company's business operations and financial results is uncertain and may be affected by various factors, including whether and when such trade measures are implemented, the timing when such measures may become effective, and the amount, scope or nature of such trade measures, and the Company's ability to execute strategies to mitigate the potential negative impacts resulting therefrom. If the Company is unable to navigate further changes in U.S. or international trade policy, it could have a material adverse impact on the Company's business and results of operations.

Removed

Risks Relating to Lithium Production and Operations

Removed

Failure to achieve production estimates for Thacker Pass, due to inaccuracies in assumptions or lower quality ore, could materially and adversely affect cash flows and profitability

Removed

This Form 10-K and the Reports contain estimates relating to future production and future production costs for Thacker Pass. No assurance can be given that production estimates will be achieved generally or at the stated costs. These production estimates are dependent on, among other things, the accuracy of mineral reserve estimates, the accuracy of assumptions regarding ore grades and recovery rates, ground conditions, physical conditions of ores, assumed metallurgical characteristics and the accuracy of estimated rates and costs of mining and processing. For Thacker Pass, ore grades or types may be lower quality than expected, which may result in levels lower than expected. The failure of the Company to achieve production estimates could have a material and adverse effect on any or all of its cash flows, profitability, results of operations and financial condition and prospects.

Reworded

The processes contemplated by the Company for production of lithium carbonate from a sedimentary deposit such as that of Thacker Pass have not previously been demonstrated at commercial scale. To mitigate this risk, the Company developed the Lithium Technical DevelopmentTech Center in Reno, NevadaNevada, ("LiTDC"), a newan integrated process testing facility in Reno, Nevada to test the process chemistry. The LiTDCTech Center continues to operate based on the Thacker Pass flowsheet processing raw ore to final battery-quality lithium carbonate to produce product samples for potential customers and partners. The results of ongoing test work to de-risk each step of the flowsheet continue to be in line with expectations. However, there are risks that the process chemistry will not be demonstrated at scale, efficiencies of recovery and throughput capacity will not be met, or that scaled production will not be cost effective or operate as expected. In addition, the novel nature of the deposit could result in unforeseen costs, additional changes to the process chemistry and engineering, and other unforeseen circumstances that could result in additional delays to develop the project or increased capital or operating costs from those estimated in the Reports, which could have a material adverse effect on the development of Thacker Pass.

Reworded

The development of lithium operations at Thacker Pass is highly dependent upon the currently projected demand for and uses of lithium-based end products. This includes lithium-ion batteries for electric vehicles and otherstationary largeenergy format batteries that currently have limited market share and whose projected adoption rates are not assured.storage. To the extent that such markets do not develop in the manner contemplated by the Company, then the long-term growth in the market for lithium products will be adversely affected, which would inhibit the potential for development or expansion of Thacker Pass, its potential commercial viability and would otherwise have a negative effect on the business and financial condition of the Company. In addition, as a commodity, lithium market demand is subject to the substitution effect in which end-users adopt an alternate commodity as a response to supply constraints or increases in market pricing. To the extent that these factors arise in the market for lithium, it could have a negative impact on overall prospects for growth of the lithium market and pricing, which in turn could have a negative effect on the Company and its projects. Finally, policies towards promoting the use of products that rely on the lithium the Company produces may change from time to time.

Added

In addition, the Company expects risks relating to market conditions including but not limited to potential variability in demand for lithium products and competition in the market by various producers. The strength of market demand for lithium product end-uses cannot be assured. Other developers and producers of lithium are currently active in the production and exploration of lithium resources and could impact the availability and pricing of lithium. Risks also relate to the Company’s assumptions relating to the buildout of the downstream battery supply chain in North America and other countries. The development of such infrastructure may be impacted by various economic factors such as inflation, currency exchange rates, tariffs, availability of capital and financing. A lack of investment or decreased investment in the North American downstream battery supply chain could lead to adverse impacts to the Company’s business, such as by affecting the prices at which the Company is able to sell its products and limiting the number of purchasers seeking to acquire lithium products.

Removed

Actual costs and production may vary due to factors such as resource availability and inflation

Removed

Feasibility reports and other mining studies, including the Reports, are inherently subject to uncertainties. Capital costs, operating costs, production and economic returns, and other estimates may differ significantly from those anticipated by the Company's current estimates, and there can be no assurance that the Company's actual capital, operating and other costs will not be higher than currently anticipated. The Company's actual costs and production may vary from estimates for a variety of reasons, including, but not limited to: lack of availability of resources or necessary supplies or equipment; inflationary pressures flowing from global supply chain shortages and increased transportation costs and other international events, which in turn are causing increased costs for supplies and equipment; increasing labor and personnel costs; unexpected construction or operating problems; cost overruns; lower than expected realized lithium prices; lower than expected ore grades; revisions to construction plans; risks and hazards associated with construction, mineral production and chemical plant operations; natural phenomena such as floods, fires, droughts or water shortages; unexpected labor shortages or strikes; general inflationary pressures, tariffs and interest and currency exchange rates. Many of these factors are beyond the Company's control and could have a material effect on the Company's business, financial condition, results of operations, and operating cash flow, including the Company's ability to service its indebtedness.

Reworded

The Company's operations are subject to all of the hazards and risks normally incidental to the exploration for, and the development and operation of, mineral properties and associated chemical plants, including an onsite sulfuric acid plant. The Company has implemented a comprehensive suite of health and safety measures designed to comply with government regulations and protect the health and safety of the Company's workforce in all areas of its business. The Company also strives to comply with environmental regulations in its operations. Nonetheless, mineral exploration, development and exploitationoperations involvesinvolve a high degree of risk, which even a combination of experience, knowledge and careful evaluation may not be able to overcome. Unusual or unexpected formations, formation pressures, fires, power outages, shutdowns due to equipment breakdown or failure, aging of equipment or facilities, unexpected maintenance and replacement expenditures, unexpected material handling problems, unexpected equipment capacity constraints, human error, labor disruptions or disputes, inclement weather, higher than forecast precipitation, flooding, shortages of water, explosions, releases of hazardous materials, deleterious elements materializing in mined resources, cave-ins, slope and embankment failures, landslides, earthquakes and industrial accidents, protests and other security issues, and the inability to obtain adequate machinery, equipment or labor due to shortages, strikes or public health issues such as pandemics, are some of the risks involved in mineral exploration and exploitation activities, which may, if as either a significant occurrence or a sustained occurrence over a significant period of time, result in a material adverse effect. The Company expects to rely on certain third-party owned infrastructure in order to successfully develop and operate its projects, such as power, utility and transportation infrastructure. Any failure of this infrastructure, or problems with achieving agreements that facilitate use of this infrastructure (if any are required), without adequate replacement or alternatives may also have a material impact on the Company.

Reworded

Increased focus on ESGsustainability matters could lead to higher costs, reduced profits and litigation risks

Reworded

Increased attention to, and societal expectations on companies to address, climate change and other environmental and social impacts, investor, regulatory and societal expectations regarding voluntary and mandatory ESG-relatedsustainability-related disclosures may result in increased costs, reduced profits, increased investigations and litigation, negative impacts on stock price and reduced access to capital.

Reworded

Moreover, while the Company may create and publish voluntary or mandatory disclosures regarding ESG-relatedsustainability-related matters from time to time, many of the statements in those voluntary disclosures are based on expectations and assumptions or hypothetical scenarios that may or may not be representative of current or actual risks or events or forecasts of expected risks or events, including the costs associated therewith. Such expectations and assumptions or hypothetical scenarios are necessarily uncertain and may be prone to error or subject to misinterpretation given the long timelines involved and the lack of an established approach to identifying, measuring and reporting on many ESGsustainability matters. Additionally, voluntary disclosures regarding ESGsustainability matters, as well as any ESG disclosures mandated by law,matters could result in private litigation or government investigation or enforcement action regarding the sufficiency or validity of such disclosures. In addition, failure or a perception (whether or not valid) of failure to pursue or implement ESG strategies or achieve ESG goals or commitments, including any GHG reduction or neutralization goals or commitments, coulddisclosures, result in privatedamage litigation and damageto the Company’s reputation, cause its investors or other stakeholders to lose confidence in the Company, or otherwise negatively impact its operations.

Reworded

Furthermore, certain public statements with respect to ESGsustainability matters, such as emissions reduction goals, other environmental targets, or other commitments addressing certain social or governance issues, are becoming increasingly subject to heightened scrutiny from public and governmental authorities, as well as other parties, related to the risk of potential “greenwashing,” (i.e.,i.e. misleading information or false claims overstating potential ESGsustainability benefits). Claims have been filed against issuers under various securities and consumer protection laws alleging that certain ESG-statements, goals or standards were misleading, false or otherwise deceptive. Additionally, certain employment practices and social initiatives are the subject of scrutiny by both those calling for the continued advancement of such policies, as well as those who believe they should be curbed, including government actors, and the complex regulatory and legal frameworks applicable to such initiatives continue to evolve. The Company cannot be certain of the impact of such regulatory, legal and other developments on its business. More recent political developments could mean that the Company faces increasing criticism or litigation risks. Such sentiment may focus on the Company’s environmental commitments (such as reducing GHGgreenhouse gas emissions) or its pursuit of certain employment or business practices or social initiatives that are alleged to be partisan in nature or are alleged to violate laws based, in part, on changing priorities of, or interpretations by, federal agencies or state governments. As a result, the Company may face increased litigation risks from private parties and governmental authorities related to its ESGsustainability efforts. In addition, any alleged claims of greenwashing against the Company or others in its industry may lead to further negative sentiment and diversion of investments. Additionally, the Company could face increasing costs as it attempt to comply with and navigate further regulatory ESG-related focus and scrutiny.

Removed

The Company also expects risks relating to market conditions including but not limited to potential variability in demand for lithium products and competition in the market by various producers. The strength of market demand for lithium product end-uses cannot be assured. Other developers and producers of lithium are currently active in the production and exploration of lithium resources and could impact the availability and pricing of lithium. Risks also relate to the Company’s assumptions relating to the buildout of the downstream battery supply chain in North America and other countries. The development of such infrastructure may be impacted by various economic factors such as inflation, currency exchange rates, tariffs, availability of capital and financing. A lack of investment or decreased investment in the North American downstream battery supply chain could lead to adverse impacts to the Company’s business, such as by affecting the prices at which the Company is able to sell its products and limiting the number of purchasers seeking to acquire lithium products.

Reworded

Global economic and political uncertainties, including the Russian war in Ukraine, Middle East conflicts, inflation, and changes in government policies, may adversely affect the Company’s business

Reworded

TheGeopolitical ongoing Russian war in Ukraine, conflict in the Middle East,conflicts, inflation and other factors continue to impact global markets and cause general economic uncertainty, the impact of which may have a material adverse effect on the Company's business, financial position, results of operations and prospects.

Reworded

The concerns over general global economic conditions, fluctuations in interest and foreign exchange rates, stock market volatility, geopolitical issues,issues and conflicts, including Russia's war in Ukraine, conflict in the Middle EastEast, including U.S. intervention in Iran, and U.S. involvement in Venezuela, supply chain disruptions and inflation have contributed to increased economic uncertainty and diminished expectations for the global economy. These considerations and others could have impacts on potential inflation, deflation, currency exchange rates, interest rates and other general economic and stock market conditions, which could adversely impact the Company’s business and financial condition. For example, we source a significant majority of the steel used for Thacker Pass from suppliers in the United Arab Emirates, which has been subject to regional hostilities related to the ongoing conflict with Iran. While a substantial portion of the Company’s required steel is already in transit, onsite, or stored in the Company’s laydown yard, we remain exposed to the risk that future shipments may be delayed, disrupted, or canceled as a result of these hostilities or other force‑majeure events.

Reworded

Changes in governments (at both the federal and state level in the U.S.) and resulting changes in domestic and foreign policy in the jurisdictions in which the Company and its competitors operate,operates, over the period that Thacker Pass is being developed and operated, may have an adverse impact on the Company’s costs of construction and operations in the form of changes to import and export restrictions, tariffs, trade agreements and trade wars, among other impacts. These events have the potential to have a material adverse effect on the Company's business, financial condition, results of operations and future prospects.

Removed

Risks Related to the Company’s Business and Securities

Reworded

GM’sConcentrated share ownership and rights of certain shareholders may influence corporate actions and diverge from other shareholders’ interests, potentially affecting liquidity and market price, amountamongst other areas

Added

The DOE currently holds a warrant providing it with the right to purchase up to 18,268,687 Common Shares (equal to 5% of the Company) and a warrant providing it with the right to purchase 8,656,509,695 non-voting units of the JV (equal to a 5% economic interest in the JV) as of the Issuance Date. Additionally, the DOE has certain registration rights, put and call rights, and an observation right in respect of the JV’s board of directors (the “JV Board”) in connection with such warrants. Finally, the DOE is a creditor of the Company pursuant to the DOE Loan.

Reworded

As a result of itstheir currentrespective shareholdingsequity interests and investor rights, each of GM and the DOE may have the ability to influence the outcome of corporate actions requiring shareholder approval, including the election of directors of the Company and the approval of certain corporate transactions. There is a risk that the interests of GM and/or the DOE may diverge from those of other shareholders and also discourage transactions involving a change of control, including transactions in which an investor, as a holder of the Company's securities, would otherwise receive a premium for the Company's securities over the then current market price. The holdings and respective rights of GM and/or the DOE could also create a risk that the Company's securities are less liquid and trade at a relative discount compared to circumstances where GM and/or the DOE did not have the ability to influence or determine matters affecting the Company.

Added

GM and the DOE have rights that may affect other security holders and the Company's actions with respect to the development of Thacker Pass through their respective investor and creditor rights, rights as a JV Partner (in the case of GM) and other rights

Removed

GM has significant influence over Thacker Pass’s development due to investor rights, its rights as a JV Partner and board representation at both the Company and Lithium Nevada Ventures, which may affect other securityholders and the Company’s actions, including the determination to make a FID in respect of Phase 1 of Thacker Pass

Reworded

There can be no certainty that the potential benefits of the JV Transaction will be fully realized. InEach addition,of inGM connection withand the JVDOE Transaction,have GM received a set of investorcertain rights, based upon certaintheir respective ownership thresholdsinterests, creditor rights (in the case of the DOE) and production commitments with(in the Company,case of GM), which may affect the rights and entitlements of other securityholders of the Company adversely and restrict certain actions of the Company, including with respect to board nomination rights, oversight, demand registration and piggy-back registration rights and participation in future equity issuances of the Company. GM also has a commercial relationship with the Company in respect of Thacker Pass and holds a 38% interest in Thacker Pass as of the date hereof.

Added

The DOE is a creditor to the Company and also holds a warrant providing it with the right to purchase at a nominal cost 8,656,509,695 non-voting units of the JV equal to a 5% economic interest in the JV as of the Issuance Date.

Reworded

In addition, pursuant to the terms of the JV Transaction, GM was granted the right to elect two of the five members of the JV’s board of directors (the “JV Board”). GM was also granted customary minority approval rights with respect to the business and governance of the JV. GM’s influence over the JV may impact the Company’s ability to continue its development of Thacker Pass on terms previously announced, and, as a result of GM’s membership on the JV Board, coupled with its various consent rights, GM may beis able to exert significant influence over the results of Thacker Pass (whether through impacting construction, further development decisions, future planning or otherwise),. includingThe DOE’s influence over the determinationJV as a result of its warrant over the JV's equity interests and as a creditor through the DOE Loan mean that the DOE may be able to makeimpact athe FIDCompany’s inability respectto ofcontinue Phaseits 1development of Thacker Pass.Pass and to impact the results of Thacker Pass as a result of its protective rights.

Removed

Upon conversion of the Orion Note, if issued, Orion may hold a substantial equity position in LAC’s business and may thereafter exercise influence over the Company

Removed

Pursuant to its terms, the Orion Note, if issued, is convertible into a significant number of the Company’s Common Shares. If Orion were to fully convert the Orion Note after issuance, or a significant portion thereof, it may receive an amount of the Company’s Common Shares totaling (but in no event exceeding) 19.99% of LAC’s outstanding Common Shares as of the date of the commitment of the Orion Investment. Consequently, Orion would be able to exercise a significant level of influence on the Company’s policies and operations and impact the outcome of any matters requiring shareholder approval. The interests of Orion with respect to matters potentially or actually involving or affecting the Company and its other shareholders, such as future acquisitions, financings and other corporate opportunities, may deviate from or conflict with the interests of the Company’s other shareholders.

Reworded

The Company’s debt agreements, including the DOE Loan and the Orion Note, if issued, contain restrictions that limit its flexibility in operating its business

Showing the first 60 of 117 changed paragraphs. The complete comparison will be part of Pro (coming soon). Meanwhile you can read the full text in the original filing.

Management's Discussion & Analysis (MD&A) (10-K Item 7)

80new paragraphs
44removed paragraphs
32reworded paragraphs
6,280 → 8,281words in section

New heading “CAPITAL EXPENDITURE AND 2026 CAPEX GUIDANCE”

New heading “Joint Venture with GM”

New heading “Equity Offerings”

New heading “Accounting and Valuation for Debt and Debt Facilities”

New heading “Accounting and Valuation for Contracts on own equity”

Removed heading “2024 OPERATING AND FINANCIAL HIGHLIGHTS”

Removed heading “The Year Ended December 31, 2024 compared with the Year Ended December 31, 2023”

Removed heading “Commencement of Development of Thacker Pass”

Largest changes (selected automatically by length and topic keywords; quoted verbatim, no commentary)

New text topics: tariff, china, supply chain, labor
“Thacker Pass Phase 1 construction costs as of December 31, 2025 and those estimated for 2026 include actual tariffs incurred (through December 31, 2025) and estimated tariff exposure (estimated for 2026 based on known information as of February 19, 2026) for equipment and construction material sourced from Canada, China, India, UAE, Turkey and the European Union. …”
see in full comparison
Reworded topics: default, covenant

Paragraph as it now reads, with added and removed wording marked:

On October 28, 2024, the Company closed thea $2.26 billion DOE Loan from the U.S.Office DOEof LPOEnergy Dominance Financing (“EDF”), previously known as the Loans Program Office under the Advanced Technology Vehicles Manufacturing (“ATVM”) Loan Program, for financing the construction of Phase 1 processing facilities at Thacker Pass. The $2.26 billion DOE Loan includesincluded principal of $1.97 billion and capitalized interest during construction, which iswas estimated to be $290$289.6 million over a three-year period (based on an interest rate of 5.2%). The DOE Loan hasoriginally had a 24-year maturity (from the date of first draw on the DOE Loan) with interest rates fixed from the date of each monthly advance for the term of the loan at applicable U.S. Treasury rates,rates without any additional credit spread. OtherThe keyDOE termsLoan includewas customaryamended covenantsby andthe eventsOWCA ofon defaultOctober for7, a2025, projectas financediscussed loanin facilitymore anddetail customary conditions precedent to loan effectiveness and advances for a project finance loan facility.below.
see in full comparison
New text topics: fine
“On the Issuance Date, the JV, the Company, B.C. Corp, the LAC JV Member, GM and the DOE, entered into a Put, Call and Exchange Agreement (the “Put, Call and Exchange Agreement”). …”
see in full comparison
Removed text
“The Year Ended December 31, 2024 compared with the Year Ended December 31, 2023”
see in full comparison
New text
“Accounting and Valuation for Debt and Debt Facilities”
see in full comparison
New text
“Accounting and Valuation for Contracts on own equity”
see in full comparison
Full comparison: every changed paragraph (156)

Green = added, red = removed. Unchanged paragraphs, 1 paragraphs where only numbers/dates changed, and tables are not shown. Read the complete text in the original filing.

Reworded

The following Management’s Discussion and Analysis (“MD&A”) provides information concerning the financial condition and results of operations of the Company and should be read in conjunction with the Company’s audited consolidated financial statements as at and for the fiscal years ended December 31, 20242025 and 20232024 (“FY 20242025” and “FY 2023,2024,” respectively), in each case, together with the notes thereto. The financial information contained in this MD&A is derived from the consolidated financial statements prepared in accordance with generally accepted accounting principles in the United States (“USU.S. GAAP”) and applicable rules and regulations of the Securities and Exchange Commission (“SEC”). The Company uses certain non-GAAP financial measures. For a detailed description of each of the non-GAAP measures used, please refer to the discussion under “Use of Non-GAAP Financial Measures and Reconciliations.” This item should be read in conjunction with the Company’s consolidated financial statements and the notes thereto included in this annual report on Form 10-K.

Added

The Company’s fiscal year is the 12-month period ending December 31. All references to “Q4 2025” and “Q4 2024” are to the fiscal quarters for the three-month periods ended December 31, 2025 and December 31, 2024 respectively. Amounts stated in this MD&A are in United States dollars, unless otherwise indicated.

Removed

On June 28, 2024, the Company determined that it no longer met the definition of a Foreign Private Issuer, and therefore no longer is entitled to rely on the foreign private issuer exemptions. As a result, beginning on January 1, 2025, the Company became required to report as a domestic U.S. filer, including filing annual reports on Form 10-K, quarterly reports on Form 10-Q, current reports on Form 8-K and proxy statements under section 14 of the Exchange Act.

Removed

In prior periods, the Company prepared its financial statements in accordance with IFRS® Accounting Standards as issued by the International Accounting Standards Board. As a consequence of becoming a domestic issuer as of January 1, 2025, the Company is required to present its financial information in U.S. GAAP. The financial information discussed herein has been prepared in accordance with U.S. GAAP for all periods presented, except as otherwise indicated. The financial information should not be expected to correspond with financial information previously presented under IFRS® Accounting Standards.

Removed

The financial statements reflect (i) the activities of the Company from and after the Separation (as defined below) and (ii) the activities of LAC North America (as defined below) on a “carve-out” basis prior to that date. Prior to Separation, LAC North America did not operate as a separate legal entity. The assets, liabilities and results of operations prior to October 3, 2023 represent those specifically identifiable to LAC North America (as defined below) including assets, liabilities and expenses relating to Thacker Pass, specified investments, transactions and balances arising from an original investment from General Motors, as well as an allocation of certain costs relating to the management of those relevant assets, liabilities, and results of operations. Such costs have been allocated from the shared corporate expenses of Lithium Americas Corp. (“Old LAC”) based on the estimated level of involvement of Old LAC management and employees with LAC North America.

Removed

The Company’s fiscal year is the 12-month period ending December 31. All references to “Q4 2024” and “Q4 2023” are to the fiscal quarters for the three-month periods ended December 31, 2024 and December 31, 2023 respectively. Amounts stated in this MD&A are in United States dollars, unless otherwise indicated.

Removed

BACKGROUND

Reworded

Lithium Americas Corp. (the “Company” or “New LAC”) is principally focused on development of Thacker Pass ("“Thacker Pass"” or the “Project”) a sedimentary-based lithium deposit located in the McDermitt Caldera in Humboldt County in north-western Nevada, USA. Thacker Pass is owned by Lithium Nevada LLC (“LN”), a wholly owned subsidiary of Lithium Nevada Ventures LLC (“Lithium Nevada Ventures”), the joint venture (“JV”) between General Motors Holdings LLC (“GM”) and the Company (together, the “JV Partners”). TheAs of March 18, 2026, the Company owns a 62% interest in Thacker Pass and will managemanages the Project (the “Manager”), and GM owns a 38% interest in Thacker Pass. The JV is consolidated in the consolidated financial statements of the Company.

Removed

The Company was initially formed for the sole purpose of acquiring ownership of the North American business assets and investments (“LAC North America”) of Old LAC, which is now named Lithium Argentina AG (formerly Lithium Americas (Argentina) Corp.) (“Lithium Argentina”), pursuant to a separation transaction (the “Separation”) that was undertaken on October 3, 2023. Upon consummation of the Separation, the Company changed its name from 1397468 B.C. Ltd to Lithium Americas Corp. Following the Separation, Lithium Argentina and the Company became independent public companies. The Separation was completed pursuant to an arrangement agreement between the Company and Old LAC. Upon completion of the Separation, Old LAC contributed to the Company, among other assets and liabilities, its interest in Thacker Pass, its investments in Green Technology Metals Limited (“GT1”) and Ascend Elements Inc. (“Ascend Elements”), certain intellectual property rights, its loan to 1339480 B.C. Ltd., and cash of $275.5 million, including $75 million to establish sufficient working capital (non-GAAP). The Company then distributed its common shares to shareholders of Old LAC in a series of share exchanges. The Separation was pro rata to the shareholders of Old LAC, so that the holders maintained the same proportionate interest in Old LAC (upon the Separation, Lithium Argentina) and the Company both immediately before and immediately after the Separation.

Removed

2024 OPERATING AND FINANCIAL HIGHLIGHTS

Reworded

2025 and SUBSEQUENT TO DECEMBER 31, 2025 FINANCIAL AND CORPORATE HIGHLIGHTS As of December 31, 2024,2025, the Company had approximately $594.2$905.6 million in cash,total cash equivalents and restricted cash.cash, including $412.6 million at the JV.

Reworded

During the year ended December 31, 2024,2025, $179.9$611.6 million of construction capital costs and other project-related costs were capitalized. To December 31, 2025, a total of $982.8 million of construction capital costs and other project-related costs have been capitalized. See the Capital Expenditure and 2026 Capital Guidance section below for more details.

Added

On October 7, 2025, the Company and the U.S. Department of Energy (“DOE”) entered into an omnibus waiver, consent and amendment (as amended the “OWCA”) for certain amendments to the Company’s loan from the DOE (“DOE Loan”). Pursuant to the OWCA, on January 30, 2026 (the “Issuance Date”), the Company issued to the DOE: (a) a warrant agreement to purchase up to 18,286,687 Common Shares of the Company at an exercise price of $0.01 per share (the “LAC Warrant”) and (b) a warrant agreement to purchase 8,656,509,695 non-voting units of the JV (the “Non-Voting Units”) at an exercise price of $0.0001 per unit (the “JV Warrant”).

Added

As of March 18, 2026, the LAC Warrant and the JV Warrant have not been exercised.

Added

The Company received its first advance on the DOE Loan of $435.0 million on October 20, 2025 and its second advance on the DOE Loan of $432 million on February 24, 2026.

Added

During 2025, the Company entered into three separate at-the-market (“ATM”) programs, the last of which was completed in January 2026. Under these programs, during the year ended December 31, 2025, the Company sold 68.2 million common shares at an average price of $5.98 per share, for aggregate net proceeds of $401.2 million after sales agent’s commission and other expenses. Subsequent to December 31, 2025, the last ATM program was completed, and the Company sold an additional 32.5 million common shares, at an average price of $5.92 per share, for net proceeds of $189.7 million after sales agent's commission and other expenses.

Added

On April 1, 2025, the JV Partners announced the final investment decision (“FID”) for construction of Phase 1 of Thacker Pass.

Reworded

SubsequentOn toApril Q4 2024 on March 6,1, 2025, the Company closed the previously announced a strategic investment of $250 million from fund entities managed by Orion Resource Partners LP (collectively, “Orion”), for the development and construction of Phase 1 of the Thacker Pass (“Orion Investment”). As part of closing, Orion haspaid committedthe toCompany purchasetotal gross proceeds of $220 million in cash for $195 million of senior unsecured convertible notes in (the aggregate principal amount of $195 million and enter into a Production Payment Agreement (“PPANotes”) whereby Orion will pay the Companyand $25 million in exchange for payments corresponding to the minerals processedproduced and gross revenue generated by Thacker Pass.Pass Orion(the has“Production alsoPayment committed,Agreement” subjector “PPA”). On declaring FID, GM and the Company contributed $100 million and $191.6 million in cash to the satisfactionJV, of certain conditions precedent, to purchase an additional $30 million in aggregate principal amount of senior unsecured convertible notes during the next two years upon request by the Company.respectively.

Added

On October 10, 2025 and October 28, 2025, fund entities managed by Orion elected to convert a total of $97.5 million in accordance with the terms of the Notes. Following the conversions, total future interest payable under the Notes has been reduced pro rata.

Added

2025 PROJECT AND CONSTRUCTION HIGHLIGHTS

Added

The Company continues to progress major construction at Thacker Pass Phase 1. Construction milestones achieved in 2025 include:

Added

As of December 31, 2025, detailed engineering design complete achieved 93%, while procurement was 60% complete.

Added

At the end of December 2025, there were approximately 950 personnel on site at Thacker Pass, including approximately 740 manual craft and 210 additional site workers. The number of personnel is expected to increase to approximately 1,800 at peak construction in 2026.

Added

In 2025, 1.69 million workhours were completed at Thacker Pass without a serious injury or lost-time incident, and the total recordable incident frequency rate was 0.21.

Added

Foundation, rebar and concrete work continue at multiple facilities throughout the processing plant, including the Filter Building, the Magnesium Sulfate Building and Warehouse Facilities.

Added

Multiple facilities at the Thacker Pass processing plant also progressed structural steel installation, including the Filter Building, Magnesium Sulfate Building and the Liquid Sulfur Tanks.

Added

The installation of certain long lead equipment commenced in Q4 2025.

Added

Active hydroseeding of disturbed areas across the site using native seeds was performed.

Added

In September 2025, the Workforce Hub (“WFH”) became partially operational and welcomed its first residents. As of February 13, 2026, there were nearly 700 residents at the WFH. Occupancy at the WFH is expected to align with the hiring and ramp-up of construction workers.

Added

The Company is growing its Operations and Business Readiness (“OBR”) team to de-risk the transition from the engineering, procurement and construction phases of Thacker Pass through commissioning, ramp up and into production and maintenance of the greenfield mining and chemical facility.

Added

As of December 31, 2025, the OBR team had 25 employees. Hiring additional OBR team members is expected to ramp up throughout 2026 in preparation for pre-commissioning and process commissioning in late 2026 and throughout 2027.

Added

Throughout 2025, the following key roles were filled: Site Operations Director, Lithium Carbonate Plant Manager, Sulfuric Acid Plant Manager, Maintenance Manager, Supply Chain Manager, Training Manager and Process Superintendent.

Added

The OBR team is currently preparing safety plans, operating procedures, multi-disciplinary training programs, emergency response training and other programs, which are being finalized and implemented.

Added

The OBR team continues to conduct factory acceptance tests of key equipment and processes, while working with these vendors to learn best practices from their customers’ existing operations.

Added

CAPITAL EXPENDITURE AND 2026 CAPEX GUIDANCE

Added

As of December 31, 2025, a total of $982.8 million of construction capital costs and other project-related costs have been capitalized, of which $862.6 million is part of the total capital expenditure (“Capex”) estimate of $2.93 billion per the Company’s Technical Reports entitled “NI 43-101 Technical Report on the Thacker Pass Project Humboldt County, Nevada, USA,” (“NI 43-101 Technical Report”) and the “S-K 1300 Technical Report on the Thacker Pass Project Humboldt County, Nevada, USA,” both dated effective December 31, 2024 (together with the NI 43-101 Technical Report, collectively referred to herein as the “Reports”).

Added

The Company is targeting a total Capex range of $1.3 billion to $1.6 billion for Thacker Pass Phase 1 for fiscal year 2026. The table below summarizes Capex cumulative to December 31, 2025 as well as 2026 Capex guidance.

Added

Capex Notes:

Added

(1)

Added

Thacker Pass Phase 1 construction costs as of December 31, 2025 and those estimated for 2026 do not include $14.1 million and $8.0 million, respectively, of community contributions that are required to be expensed under US GAAP, though these were included in the $2.93 billion Capex estimate per the Company’s Reports.

Added

(2)

Added

Thacker Pass Phase 1 construction costs as of December 31, 2025 and those estimated for 2026 include actual tariffs incurred (through December 31, 2025) and estimated tariff exposure (estimated for 2026 based on known information as of February 19, 2026) for equipment and construction material sourced from Canada, China, India, UAE, Turkey and the European Union. The Company has been working toward limiting the effect of any potential tariffs on the Company’s construction supply chain, with approximately 75% of the total capital project cost structure related to labor, contractors and other services not expected to be directly affected by any potential tariffs. The Company continues to monitor closely potential tariff exposure; however, changes in tariffs and trade restrictions can be announced with little or no advance notice.

Added

(3)

Added

Other capitalized development costs are required to be capitalized under US GAAP, though these were not included in $2.93 billion Capex estimate per the Company’s Reports.

Removed

On October 28, 2024, the Company and the U.S. Department of Energy’s (“DOE”) Loan Programs Office (“LPO”) closed a $2.26 billion loan under the Advanced Technology Vehicles Manufacturing (“ATVM”) Loan Program (the “DOE Loan”) for financing the construction of the processing facilities at Thacker Pass, to produce an initial 40,000 tonnes per annum of battery grade lithium carbonate (“Phase 1”). Closing of the DOE Loan follows receipt of a Conditional Commitment from the DOE on March 12, 2024.

Removed

On October 15, 2024, the Company and GM entered into a new investment agreement (“Investment Agreement”) to establish a joint venture (“JV”) for the purpose of funding, developing, constructing and operating Thacker Pass (“JV Transaction”). GM acquired a 38% interest in Thacker Pass for $625 million in total committed cash and letters of credit, comprised of a $430 million commitment of direct cash funding to the JV to support the construction of Phase 1 of Thacker Pass and a $195 million letter of credit facility (“LC Facility”) that can be used as collateral to support reserve account requirements under the DOE Loan. Lithium Americas owns a 62% interest in Thacker Pass and will manage the Project. On December 23, 2024, the Company announced the closing of the JV Transaction whereby GM contributed $330 million of cash into the JV alongside $138 million of cash funding from the Company. The remaining $100 million cash contribution from GM, and Lithium Americas’ $192 million contribution, is to be contributed at FID for Phase 1. GM will post the LC Facility prior to first draw on the DOE Loan, which is expected to occur sometime in Q3 2025.

Removed

In connection with the JV, GM’s offtake agreement for up to 100% of production volumes from Phase 1 of Thacker Pass was extended to 20 years and GM entered into an additional offtake agreement for up to 38% of Phase 2 production for 20 years, and will retain its right of first offer on the remaining balance of Phase 2 production volumes.

Removed

Together with the DOE Loan and the investments from both GM and Orion, the Company expects to achieve fully funded status at the project and corporate level for the development and construction of Phase 1 of Thacker Pass for the duration of construction.

Removed

In the fourth quarter of 2024, the Company provided Bechtel and other major contractors with limited full notice to proceed (“FNTP”) to de-risk the construction schedule and continue to target completion in late 2027. The Company continues to focus on de-risking project execution by advancing detailed engineering, project planning and procurement packages.

Removed

In August 2024, the Company received approval for a $11.8 million grant from the U.S. Department of Defense to support an upgrade of the local power infrastructure and to help build a transloading facility.

Removed

On April 22, 2024, the Company completed an underwritten public offering (the “Offering”) of 55 million Common Shares at a price of $5.00 per Common Share (the “Issue Price”) for aggregate gross proceeds to the Company of $275 million. The net proceeds from the Offering of approximately $262 million are intended to fund the advancement of construction and development of Thacker Pass.

Reworded

On October 28, 2024, the Company closed thea $2.26 billion DOE Loan from the U.S.Office DOEof LPOEnergy Dominance Financing (“EDF”), previously known as the Loans Program Office under the Advanced Technology Vehicles Manufacturing (“ATVM”) Loan Program, for financing the construction of Phase 1 processing facilities at Thacker Pass. The $2.26 billion DOE Loan includesincluded principal of $1.97 billion and capitalized interest during construction, which iswas estimated to be $290$289.6 million over a three-year period (based on an interest rate of 5.2%). The DOE Loan hasoriginally had a 24-year maturity (from the date of first draw on the DOE Loan) with interest rates fixed from the date of each monthly advance for the term of the loan at applicable U.S. Treasury rates,rates without any additional credit spread. OtherThe keyDOE termsLoan includewas customaryamended covenantsby andthe eventsOWCA ofon defaultOctober for7, a2025, projectas financediscussed loanin facilitymore anddetail customary conditions precedent to loan effectiveness and advances for a project finance loan facility.below.

Added

On October 7, 2025, the Company and the DOE entered into the OWCA for certain amendments to the DOE Loan. Pursuant to the OWCA:

Added

The DOE Loan expected total loan amount decreased to $2.23 billion due to estimated capitalized interest during construction decreasing to $256.0 million, while the DOE Loan principal remained the same at $1.97 billion. The interest rate that will be applied to amounts drawn under the DOE Loan remained unchanged at the applicable long-dated U.S. Treasury rate from the date of each draw with 0% spread. The DOE Loan tenor was set to approximately 23 years from date of first draw on the DOE Loan. The DOE Loan has a maturity date of July 20, 2048.

Added

The DOE agreed to defer $184.0 million of scheduled debt service obligations under the DOE Loan, which were to occur in the first five years of loan repayment, with the total deferred balance reallocated across the remaining payment periods to maturity.

Added

The Company is to contribute an additional $120.0 million to DOE Loan reserve accounts, to be funded within 12 months of the OWCA.

Added

The Company agreed to issue to the DOE the LAC Warrant and the JV Warrant subject to customary conditions to be finalized through definitive documents and corporate approvals.

Added

On January 30, 2026 (the “Issuance Date”), the Company issued to the DOE: (a) the LAC Warrant providing for, among other things, the right to purchase up to 18,268,687 Common Shares of the Company, which is equal to 5% of the Company’s total outstanding shares as of the Issuance Date, at an exercise price of $0.01 per share, exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms and (b) the JV Warrant, providing for, amongst other things, the right to purchase 8,656,509,695 Non-Voting Units, which is equal to a 5% economic interest in the JV as of the Issuance Date, at an exercise price of $0.0001 per unit, subject to customary anti-dilution adjustments and other terms. Each of the LAC Warrant and the JV Warrant shall be automatically exercised in full on a cashless basis immediately prior to expiration, and the LAC Warrant shall additionally be exercised in full via cashless exercise on the 12-month anniversary of the Issuance Date and on each one-year anniversary of such date thereafter if the VWAP of the Common Shares over the 15 Trading Days ending immediately prior to such date exceeds $30.00 per share (as adjusted).

Added

On the Issuance Date, the JV, the Company, B.C. Corp, the LAC JV Member, GM and the DOE, entered into a Put, Call and Exchange Agreement (the “Put, Call and Exchange Agreement”). Under the Put, Call and Exchange Agreement, the DOE has a put right (the “DOE Put”) to require GM to elect to either (i) purchase, or cause the JV to purchase, the JV Warrant and any Non-Voting Units issued upon conversion thereof, as applicable (a “JV Warrant Sale”), or (ii) subject to applicable exchange approvals and compliance with securities laws, cause the JV Warrant and any Non-Voting Units issued upon conversion thereof, as applicable, to be exchanged for a warrant to purchase a number of the Company’s Common Shares (a “JV Warrant Exchange”) that would result in the DOE holding a percentage of the total issued and outstanding Common Shares equal to the then applicable Warrant Conversion Rate (as defined below). Additionally, the exercise (including any automatic exercise) of the LAC Warrant shall be deemed to be delivery of a put notice pursuant to the Put, Call and Exchange Agreement. The sale price for a JV Warrant Sale will be mutually determined in good faith by GM and the DOE. If GM and the DOE cannot agree on the sale price for a JV Warrant Sale within 60 days of delivery of the put notice or if the JV Warrant Sale is not completed within 90 days of the delivery of the put notice, the parties will cause a JV Warrant Exchange to occur. The (“Warrant Conversion Rate”) will be, as of the time of determination, the product of (i) 100 multiplied by (ii) the quotient obtained by dividing (A) the number of fully diluted Non-Voting Units in the JV held by the DOE by (B) the number of outstanding units in JV held by the LAC JV Member plus the number of fully diluted Non-Voting Units in the JV held by the DOE. The number of outstanding units in the JV held by the LAC JV Member is subject to adjustment in connection with (i) the funding of any incremental capital contribution to the JV or (ii) the transfer by the LAC JV Member of any units in the JV, in each case in accordance with the Amended and Restated Limited Liability Company Agreement of the JV.

Added

In addition, from and after the earlier of the Scheduled Substantial Completion Date and the Substantial Completion Date of Thacker Pass (as such dates are defined in the Loan Arrangement Reimbursement Agreement), GM has a call right (the “GM Call”) to elect to effect, or cause the JV to effect, a JV Warrant Sale if a price can be agreed upon between GM and the DOE within 60 days of the delivery of the call notice. If GM and the DOE cannot agree on the sale price within 60 days of delivery of the call notice or if the JV Warrant Sale is not completed within 90 days of the delivery of the call notice, the parties will cause a JV Warrant Exchange to occur.

Showing the first 60 of 156 changed paragraphs. The complete comparison will be part of Pro (coming soon). Meanwhile you can read the full text in the original filing.

What changed in the latest 10-Q

Comparing 10-Q filed 2026-08-13 (period ending 2026-06-30) with 10-Q filed 2026-05-14 (period ending 2026-03-31).

Risk Factors (10-Q Part II, Item 1A)

7new paragraphs
0removed paragraphs
1reworded paragraphs
35 → 803words in section

New heading “Existing and future financings could materially dilute current shareholders’ interests, impose significant restrictions, increase indebtedness and adversely affect the Company’s financial condition and share price.”

Largest changes (selected automatically by length and topic keywords; quoted verbatim, no commentary)

New text topics: default, interest rate
“Any indebtedness could require the Company to dedicate a substantial portion of its future cash flows to debt service thereby reducing cash flow available for operating and business activities; limit management’s flexibility in operating the business and responding to changing market conditions; increase the Company’s vulnerability to economic downturns; restrict the Company’s ability to obtain additional financing, make investments, sell assets, lease equipment or engage in business combinations; …”
see in full comparison
New text
“Existing and future financings could materially dilute current shareholders’ interests, impose significant restrictions, increase indebtedness and adversely affect the Company’s financial condition and share price.”
see in full comparison
New text topics: interest rate
“The Company’s ability to obtain additional financing on acceptable terms, or at all, will depend on various factors, including capital market conditions, interest rates, investor sentiment and the Company’s operating performance. Failure to secure financing when needed could require the Company to postpone, reduce, abandon or terminate development or operations at Thacker Pass, result in dilution of its ownership interest, and have a material adverse effect on the Company’s business, financial condition, results of operations, cash flows and prospects.”
see in full comparison
New text
“Future equity issuances or the conversion or exercise of outstanding notes, warrants, restricted share units or other convertible securities, including further conversion of the Orion Note and the issuance of warrants to the DOE that may be convertible into a significant number of common shares, could result in substantial dilution and decline in the market price of the Company’s common shares. …”
see in full comparison
New text
“Such financing may be obtained through the issuance of common shares, preferred shares, options, warrants, other equity securities of equal or senior rank, convertible debt securities, or by way of project level investments, offtake and royalty arrangements, debt instruments or other financing vehicles and may not require shareholder approval. Under certain circumstances, the Company may also issue common shares to GM and/or the US DOE in connection with the JV, which could further dilute the Company’s ownership interest in Thacker Pass. …”
see in full comparison
New text
“Sales of common shares by the Company or its stockholders, or the perception that such sales may occur, could cause the market price of the Company’s common shares to decline and make it more difficult to raise capital on favorable terms. The Company cannot predict the size of future issuances or sales of the Company’s common shares or the effect, if any, that future issuances and sales of the Company’s common shares will have on the market price of the Company’s common shares.”
see in full comparison
Full comparison: every changed paragraph (8)

Green = added, red = removed. Unchanged paragraphs and tables are not shown. Read the complete text in the original filing.

Reworded

ThereExcept as set forth below, there have been no material changes to the risk factors disclosed in Part I. Item 1A. Risk Factors of the Company's annual report on Form 10-K for the year ended December 31, 2025.

Added

Existing and future financings could materially dilute current shareholders’ interests, impose significant restrictions, increase indebtedness and adversely affect the Company’s financial condition and share price.

Added

The Company has significant capital requirements and may need to access the capital markets to obtain additional short-term and long-term financing in connection with, among other things, the development and operation of Thacker Pass, future exploration, development and acquisition plans, repayment of outstanding indebtedness, issuances and exercises under the Company’s equity incentive plan.

Added

Such financing may be obtained through the issuance of common shares, preferred shares, options, warrants, other equity securities of equal or senior rank, convertible debt securities, or by way of project level investments, offtake and royalty arrangements, debt instruments or other financing vehicles and may not require shareholder approval. Under certain circumstances, the Company may also issue common shares to GM and/or the US DOE in connection with the JV, which could further dilute the Company’s ownership interest in Thacker Pass. Existing and future equity financing arrangements could materially dilute existing shareholders’ ownership interests, decrease the amount of cash available for dividends payable on common shares or be nil, decrease the relative voting of outstanding common shares, decrease the value of the Company’s securities and reduce the value of their investment.

Added

Future equity issuances or the conversion or exercise of outstanding notes, warrants, restricted share units or other convertible securities, including further conversion of the Orion Note and the issuance of warrants to the DOE that may be convertible into a significant number of common shares, could result in substantial dilution and decline in the market price of the Company’s common shares. In connection with the Orion Investment, the Company also entered into a registration rights agreement with Orion pursuant to which the Company agreed, among other things, to register for resale any shares issued upon conversion of the Orion Note. Pursuant to the obligations set forth in the registration rights agreement, dated April 1, 2025, by and among the Company and an entity affiliated with Orion, the Company has registered for resale by Orion up to 43,707,080 common shares, of which, 25,793,651 common shares were issued upon conversion in 2025. Additionally, the Company has issued certain warrants to the DOE, which will be convertible pursuant to their terms into common shares in an amount that may equal up to approximately 13% of the Company’s issued and outstanding common shares. In connection with the issuance of such warrants, the Company entered into a registration rights agreement with the DOE pursuant to which the Company agreed to file a registration statement to register the resale of the common shares underlying the warrants. The Company has also agreed to register up to 72,553,609 shares issuable to Yorkville upon conversion of the Yorkville Debentures.

Added

Sales of common shares by the Company or its stockholders, or the perception that such sales may occur, could cause the market price of the Company’s common shares to decline and make it more difficult to raise capital on favorable terms. The Company cannot predict the size of future issuances or sales of the Company’s common shares or the effect, if any, that future issuances and sales of the Company’s common shares will have on the market price of the Company’s common shares.

Added

Any indebtedness could require the Company to dedicate a substantial portion of its future cash flows to debt service thereby reducing cash flow available for operating and business activities; limit management’s flexibility in operating the business and responding to changing market conditions; increase the Company’s vulnerability to economic downturns; restrict the Company’s ability to obtain additional financing, make investments, sell assets, lease equipment or engage in business combinations; increase the Company’s vulnerability to interest rates as the rates applicable to outstanding indebtedness may vary with prevailing interest rates; place the Company at a competitive disadvantage relative to competitors with less leverage and restrictive terms from indebtedness; and increase the risk of default on its debt obligations.

Added

The Company’s ability to obtain additional financing on acceptable terms, or at all, will depend on various factors, including capital market conditions, interest rates, investor sentiment and the Company’s operating performance. Failure to secure financing when needed could require the Company to postpone, reduce, abandon or terminate development or operations at Thacker Pass, result in dilution of its ownership interest, and have a material adverse effect on the Company’s business, financial condition, results of operations, cash flows and prospects.

Management's Discussion & Analysis (MD&A) (10-Q Part I, Item 2)

28new paragraphs
30removed paragraphs
70reworded paragraphs
7,538 → 6,552words in section

New heading “Yorkville Advisors”

Removed heading “Common Shares Offering”

Removed heading “Assessment of Impairment of Thacker Pass”

Removed heading “Accounting for Joint Venture with GM”

Removed heading “Accounting and Valuation for Debt and Debt Facilities”

Removed heading “Accounting and Valuation for Contracts on Own Equity”

Removed heading “Royalties and Production Payments”

Largest changes (selected automatically by length and topic keywords; quoted verbatim, no commentary)

Reworded topics: tariff, inflation, labor

Paragraph as it now reads, with added and removed wording marked:

Given the advanced level of detailed engineering,engineering achieved, the Company has commenced a definitive capital estimate, targeting completion inby the second halfend of Q3 2026. Advanced levels of engineering and procurement is expected to enable the team to estimate remaining quantities and materials with higher confidence. The Company will use current data to assess remaining labor needs and productivity rates for the estimate and will incorporate recent and unexpected developmentsdevelopments, including the implications offrom tariffs, conflicts in the Middle East conflict impacts,East, fuel price increasesprices, and other inflationary increases that were not included in the total Capex estimate of $2.93 billion per the Company’s Technical Report. TheDuring totalQ2 Capex estimate of $2.93 billion did not include any exposure to tariffs. The Company estimates2026, the totalcost potential exposure to tariffsenvironment for activities associated with Thacker Pass Phasewas 1also constructionunfavorably costsimpacted toby beitems approximatelysuch $80as: millionreduced toopen $120sea million,lane availability, reductions in the availability of U.S. fabrication capacity, constraints in U.S. logistics, further inflationary pressures as well as an increasingly competitive skilled labor market. Further, total associated tariff exposure, the majority of which is expected to be incurred during 2026.2026, is estimated between $80 million and $100 million.
see in full comparison
Removed text topics: impairment
“Assessment of Impairment of Thacker Pass”
see in full comparison
Removed text topics: impairment
“The Company reviews and evaluates its long-lived assets for impairment when events or changes in circumstances indicate that the related carrying amounts may not be recoverable. Once it is determined that impairment exists, an impairment loss is measured as the amount by which the asset carrying value exceeds its fair value. …”
see in full comparison
Removed text
“Accounting and Valuation for Debt and Debt Facilities”
see in full comparison
Removed text
“Accounting and Valuation for Contracts on Own Equity”
see in full comparison
Removed text
“Accounting for Joint Venture with GM”
see in full comparison
Full comparison: every changed paragraph (128)

Green = added, red = removed. Unchanged paragraphs, 3 paragraphs where only numbers/dates changed, and tables are not shown. Read the complete text in the original filing.

Reworded

The following Management’s Discussion and Analysis (“MD&A”) provides information concerning the Company’s financial condition and results of operations of the Company and should be read in conjunction with the Company’s unaudited condensed consolidated interim financial statements and the notes thereto for the three and six months ended MarchJune 31,30, 2026 and audited consolidated financial statements and the notes thereto for the years ended December 31, 2025 and 2024 (“FY 2025” and “FY 2024,” respectively), together with the notes thereto.. The financial information contained in this MD&A is derived from the unaudited condensed consolidated interim financial statements prepared in accordance with generally accepted accounting principles in the United States (“U.S. GAAP”) and applicable rules and regulations of the Securities and Exchange Commission (“SEC”). The Company uses certain non-GAAP financial measures. For a detailed description of each of the non-GAAP measures used, please refer to the discussion under “Use of Non-GAAP Financial Measures and Reconciliations.” This item should be read in conjunction with the Company’s unaudited condensed consolidated interim financial statements and the notes thereto included in this Form 10-Q.

Reworded

The Company’s fiscal year is the 12-month period ending December 31. All references to “Q1Q2 2026” and “Q1Q2 2025” are to the fiscal quarters for the three-month periods ended MarchJune 31,30, 2026 and MarchJune 31,30, 2025, respectively. All references to “YTD Q2 2026” and “YTD Q2 2025” are to the six-month periods ended June 30, 2026 and June 30, 2025, respectively. Amounts stated in this MD&A are in United States dollars, unless otherwise indicated.

Reworded

Lithium Americas Corp. (the “Company”) is principally focused on development of Thacker Pass (“Thacker Pass” or the “Project”) a sedimentary-based lithium depositproject located in the McDermitt Caldera in Humboldt County in north-western Nevada, U.S. Thacker Pass is owned by Lithium Nevada LLC (“LN”), a wholly owned subsidiary of Lithium Nevada Ventures LLC (“Lithium Nevada Ventures”), the joint venture (“JV”) between General Motors Holdings LLC (“GM”) and the Company (together, the “JV Partners”). As of MayAugust 13,12, 2026, the Company ownsowned a 62% interest in Thacker Pass and managesmanaged the Project, GM ownsowned a 38% interest in Thacker Pass, and the DOE ownsowned a warrant to purchase 8,656,509,695 non-voting units of the JV, which was equal to a 5% economic interest in the JV Warranton January 30, 2026 (asthe defined“Issuance belowDate”), at an exercise price of $0.0001 per unit (the “JV Warrant”). The JV is consolidated in the unaudited condensed consolidated interim financial statements of the Company.

Reworded

As of MarchJune 31,30, 2026, the Company had approximately $1.2$1.3 billion total cash and restricted cash, including $529$530.3 million at the Thacker Pass JV level.

Removed

On January 26, 2026, the Company completed an at-the-market (“ATM”) equity program established on November 13, 2025 (the “November 2025 ATM Program”). The Company issued and sold an aggregate total of 43.3 million common shares at an average price of $5.78 per share pursuant to the November 2025 ATM Program, for aggregate net proceeds of $246.7 million after sales agent’s commission and other expenses. Of these amounts, during Q1 2026, the Company issued and sold 32.5 million common shares at an average price of $5.92 per share, for aggregate net proceeds of $189.7 million after sales agent commission and other expenses.

Removed

On February 24, 2026, the Company received its second advance on the U.S. Department of Energy (the “DOE”) loan (“DOE Loan”) of $432 million.

Reworded

On March 19, 2026, the Company entered into an at-the-market (“ATM”) equity program, pursuant to which the Company may sell its common shares, no par value, up to a maximum aggregate offering price of $250 million (the “March 2026 ATM Program”). Use of netNet proceeds forreceived from the March 2026 ATM Program includesmay be used for general corporate purposes, which may include funding of corporate and project overhead expenses, financing ofoverhead, capital expenditures, repaymentdebt of indebtednessrepayment, and additions to working capital. As of MarchJune 31, 2026, the Company did not issue or sell any common shares nor receive any net proceeds pursuant to the March 2026 ATM Program. Subsequent to March 31,30, 2026, the Company issued and sold an aggregate total of 2.313.0 million common shares at an average price of $5.20$5.36 per share pursuant to the March 2026 ATM Program, for aggregate net proceeds of $11.2$68.5 million after sales agentagent’s commission and other expenses. Subsequent to Q2 2026, the Company issued and sold 1.1 million common shares at an average price of $3.87 per share for aggregate net proceeds of $4.2 million after sales agent’s commission and other expenses.

Added

On June 3, 2026, the Company received its third advance on the U.S. Department of Energy (the “DOE”) loan (“DOE Loan”) of $342 million. Cumulative advances total $1.209 billion.

Added

On August 5, 2026, the Company entered into a securities purchase agreement (the “Purchase Agreement”) with YA II PN, Ltd., an affiliate of Yorkville Advisors Global, LP (“Yorkville”), for up to $175 million in aggregate principal amount of subordinated convertible debentures (the “Yorkville Debentures”). At the initial closing, the Company has agreed to issue $150 million in Yorkville Debentures. The Company retains the right to issue up to an additional $25 million in Yorkville Debentures in one or more subsequent closings at its discretion, subject to conditions as further described in the Purchase Agreement. See Note 16 – Subsequent Events – Yorkville Convertible Debentures and Yorkville Advisors below for further discussion.

Reworded

As of MayAugust 13,12, 2026, the Company had 351,062,478363,042,943 shares issued and outstanding.

Removed

On January 30, 2026 (the “Issuance Date”), pursuant to the omnibus waiver, consent and amendment (as amended, the “OWCA”) entered into by the Company and the DOE on October 7, 2025, the Company issued to the DOE a warrant to purchase up to 18,268,687 common shares, which was equal to 5% of the Company’s outstanding total shares as of the Issuance Date, at an exercise price of $0.01 per share (the “LAC Warrant”), exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms set forth in the LAC Warrant. Additionally, the JV issued to the DOE a warrant to purchase 8,656,509,695 non-voting units of the JV, which was equal to a 5% economic interest in the JV as of the Issuance Date, at an exercise price of $0.0001 per unit (the “JV Warrant”), exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms set forth in the JV Warrant.

Reworded

The Company continues to progress major construction of the processing plant at Thacker Pass Phase 1, targeting mechanical completion in late 2027. As of MarchJune 31,30, 2026:

Reworded

A total of 2.433.42 million workhours were completed at Thacker Pass without a serious injury or lost-time incident, andwith a total recordable incident frequency rate of 0.25.0.58.

Reworded

A total of $1.3$1.8 billion of construction capital costs and other project-related costs havehad been capitalized, of which $1.1$1.6 billion is part of the total capital expenditure (“Capex”) estimate of $2.93 billion per the Company’s Technical Report entitled “NI 43-101 Technical Report on the Thacker Pass Project Humboldt County, Nevada, USA,” effective December 31, 2024 (“Technical Report”). The Company continues to target a total capexCapex range of $1.3 billion to $1.6 billion for Thacker Pass Phase 1 for fiscal year 2026. See the Capital Expenditure and 2026 Capex Guidance section below for more details.

Reworded

Detailed engineering design completed surpassed 95%, while procurement wasexceeded over 70% complete,80%, including the shipment of major plant materials and equipment.

Reworded

ThereOver 1,600 personnel were approximately 1,065 personnel on site, and on-site personnel levels are expected to increase to over 2,000 in the second half of 2026.

Reworded

ThereOver 1,500 workers were over 1,000 workers residing at the Company’s all-inclusive housing facility for construction workers in Winnemucca (the “Workforce Hub” or “WFH”).

Reworded

Long-lead equipment has beencontinued arriving to eitherat Thacker Pass orand the fabrication yard in Winnemucca, including the 115KV Main Transformer, Auxiliary Boiler, Air Cooled Heat Exchangers, Fin Fan Cooler, Duplex Stack and Bicarbonate Reactors. Additional long-lead items that have started their delivery to site include the Thickener Steel and Shell Plates, Filter Presses, Steam Turbine Generator and SS Converter.Winnemucca. Outstanding long-lead items are expected to be delivered throughout 2026, along with other equipment and construction materials.

Reworded

Over 75%85% of the structural steel for Thacker Pass, which is sourced from the United Arab Emirates, is in transit or has arrived on site at Thacker Pass or the laydown yard in Winnemucca. The balance is expected in Q3 2026. The Company and Bechtel have worked with the steel supplier to attempt to limitminimize the effectsimpact of the Middle East conflict, including the closure of the Strait of Hormuz, to minimize impacts on the fabrication and shipment of steel to Thacker Pass. Predominantly, theThe Company has successfully re-routed steel through the Port of Jeddah.

Reworded

Development milestones achieved to date at Thacker Pass during Q2 2026 include:

Added

Completing upgrades to the high voltage power line connecting Thacker Pass to the local power grid.

Added

Placement of the first Electrical Room, 115kV Power Transformer and Control Enclosures.

Removed

The first cable pulls on the module pipe racks commenced in March 2026.

Reworded

StructuralProgressing structural steel at the Filter Building, Magnesium Sulfate Building progresses, withand the secondLithium floorCarbonate being installed.Building.

Added

Deliveries of approximately 100 prefabricated pipe rack modules, with pre-installed piping manufactured in Winnemucca. Deliveries are expected to continue throughout Q3 2026.

Added

Commencement and continuation of key equipment installation at the following facilities:

Added

Lithium Carbonate Crystallizer: Bicarbonate Reactor;

Added

Magnesium Sulfate Building: Turbo Fans, Stage 4 Crystallizer;

Added

Filter Building: Air Compressors and Receivers, Conveyor Tail Pulleys, Neutralization Filter Discharge Conveyors;

Added

Countercurrent Decantation and Run-of-Mine areas: Thickener Steel and Shell Plates;

Added

Sulfuric Acid Plant: Fin Fan Coolers, SS Converter, Steam Turbine Generator, Main Compressor, Cold Interpass Heat Exchanger, Hot Interpass Heat Exchanger and the 198-foot-tall Duplex Plant Stack.

Added

The following are expected development milestones for the second half of 2026:

Added

All main concrete required at the site is expected to be completed.

Added

Early commissioning of utilities in the individual plants is expected to commence.

Removed

Installation of key equipment commenced at the following facilities: Bicarbonate Reactors for the Lithium Carbonate Crystallizer, Pillers for Magnesium Sulfate, Air Compressors and Conveyor Tail Pulley’s for the Filter Building, Thickener Steel and Shell Plants in the Countercurrent Decantation and Run-of-Mine areas, and Fin Fan Coolers and SS Converter for the Sulfuric Acid Plant.

Reworded

Given the advanced level of detailed engineering,engineering achieved, the Company has commenced a definitive capital estimate, targeting completion inby the second halfend of Q3 2026. Advanced levels of engineering and procurement is expected to enable the team to estimate remaining quantities and materials with higher confidence. The Company will use current data to assess remaining labor needs and productivity rates for the estimate and will incorporate recent and unexpected developmentsdevelopments, including the implications offrom tariffs, conflicts in the Middle East conflict impacts,East, fuel price increasesprices, and other inflationary increases that were not included in the total Capex estimate of $2.93 billion per the Company’s Technical Report. TheDuring totalQ2 Capex estimate of $2.93 billion did not include any exposure to tariffs. The Company estimates2026, the totalcost potential exposure to tariffsenvironment for activities associated with Thacker Pass Phasewas 1also constructionunfavorably costsimpacted toby beitems approximatelysuch $80as: millionreduced toopen $120sea million,lane availability, reductions in the availability of U.S. fabrication capacity, constraints in U.S. logistics, further inflationary pressures as well as an increasingly competitive skilled labor market. Further, total associated tariff exposure, the majority of which is expected to be incurred during 2026.2026, is estimated between $80 million and $100 million.

Removed

Work to enhance reliability for grid power from the local electric utility cooperative, by upgrading six regional substations and switching stations, was completed in March 2026, ahead of schedule.

Reworded

Construction at the Company’s Transload Terminal (“TLT”) west of Winnemucca commencedcontinues. inIn MarchQ2 2026, withthe completiongeneral site and railroad grading were completed and installation of rail stabilization (geo-membrane) and sub-ballast commenced. Completion of the TLT is targeted in 2027 to align with start upstartup at Thacker Pass. The TLT is approximately 60 miles from Thacker Pass, adjacent to the rail line, and is intended to support operations by serving as a critical logistics hub for the Project’soperation’s reagents.

Added

During Q2 2026, the Company delivered a $5.0 million commitment to the Fort McDermitt Paiute and Shoshone Tribe’s Building Fund, in accordance with its obligations under the Community Benefits Agreement. The funds will support plans to rebuild a Travel Plaza, which was lost to fire in September 2020. An additional $0.4 million has been contributed to the tribe for workforce training, cultural monitoring and administrative purposes.

Reworded

As of MarchJune 31,30, 2026, a total of $1.3$1.8 billion of construction capital costs and other project-related costs havehad been capitalized, of which $1.1$1.6 billion is part of the total Capex estimate of $2.93 billion per the Company’s Technical Report. The Company continues to target a total Capex range of $1.3 billion to $1.6 billion for Thacker Pass Phase 1 for fiscal year 2026.

Reworded

The table below summarizes Capex duringin the quarterthree and six months ended MarchJune 31,30, 2026, cumulative Capex to MarchJune 31,30, 2026, as well as the Company’s 2026 Capex guidance.

Removed

Capex Notes:

Removed

(1)

Reworded

Thacker Pass Phase 1 construction costs cumulative to MarchJune 31,30, 2026 and those estimated for fiscal year 20262026, do not include $14.1$19.5 million and $8.0 million, respectively, of community contributions that are required to be expensed under U.S. GAAP, though these were included in the $2.93 billion Capex estimate per the Company’s Technical Report.

Removed

(2)

Reworded

Thacker Pass Phase 1 construction costs ascumulative ofto MarchJune 31,30, 2026, and those estimated for fiscal year 2026, include actual tariffs incurred (through MarchJune 31,30, 2026. Thacker Pass Phase 1 construction costs estimate for fiscal year 2026) andalso include estimated tariff exposure, primarily for equipment and construction materials sourced from Canada, China, India, UAE, Turkey and the European Union. The Company has been working toward limiting the effect of any potential tariffs on its construction supply chain, with approximately 75% of the total capital project cost structure related to labor, contractors and other services not expected to be directly affected by any potential tariffs. The Company continues to closely monitor potential tariff exposure; however, changes in tariffs and trade restrictions can be announced with little or no advance notice.

Removed

(3)

Reworded

Other capitalized development costs are required to be capitalized under U.S. GAAP, though these were not included in the $2.93 billion Capex estimate per the Company’s Technical Report.

Reworded

The DOE and the Company’s subsidiary, LN, executed the DOE Loan on October 28, 2024 for a construction facility with a maximum borrowing of $1.97 billion plus up to $289.6 million of capitalized interest for a total of $2.26 billion, provided under the Advanced Technology Vehicles Manufacturing (“ATVM”) Loan Program, to fund eligible construction costs of Thacker Pass, over the period from the first advancePass through no later than November 30, 2028. The DOE Loan agreement was amended on December 20, 2024 to accommodate the formation of Lithium Nevada Ventures, aand JVfurther withamended GMon October 7, 2025 pursuant to ownan aomnibus 100%waiver, consent and amendment (as amended, the “OWCA”), which reduced the expected total loan amount to $2.23 billion (reflecting lower estimated capitalized interest induring LN,construction whichof owns$256 Thacker Pass.million).

Removed

On October 7, 2025, the Company and the DOE entered into an omnibus waiver, consent and amendment (as amended the “OWCA”) for certain amendments to the Company’s DOE Loan. As part of the OWCA, the DOE Loan’s expected total loan amount decreased to $2.23 billion due to estimated capitalized interest during construction decreasing to $256 million, while the DOE Loan’s principal remained the same at $1.97 billion.

Removed

The Company issued to the DOE the LAC Warrant to purchase up to 18,268,687 common shares, which was equal to 5% of the Company’s outstanding total shares as of the Issuance Date, at an exercise price of $0.01 per share, exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms set forth in the LAC Warrant.

Reworded

The Company issued to the DOE a warrant to purchase up to 18,268,687 common shares (the “LAC Warrant”), which was equal to 5% of the Company’s outstanding total shares as of the Issuance Date, at an exercise price of $0.01 per share, and the JV issued to the DOE the JV Warrant to purchase 8,656,509,695 non-voting units of the JV,JV (together with the LAC Warrant, the “Warrants”), which was equal to a 5% economic interest in the JV as of the Issuance Date, at an exercise price of $0.0001 per unit,unit. Each Warrant is exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms set forth in the JVrespective Warrant.

Reworded

TheIn connection with these issuances, the JV, the Company, 1339480 B.C. Ltd., LAC US Corp. (the “LAC JV Member”), GM and the DOE, entered into a Put, Call and Exchange Agreement (the “Put, Call and Exchange Agreement”), under which the DOE has the right tomay require GM to either purchase the JV Warrant (or cause the JV to do so) at a mutually agreed price, or, failing agreement,agreement on price, exchange the JV Warrantit for the Company’sCompany common sharesshares. basedGM onhas a definedcorresponding warrantcall conversion rate. In addition,right following substantial completion of Thacker Pass, GM has a call right to trigger the same sale or exchange mechanics if pricing cannot be agreed within specified timeframes.Pass.

Reworded

As of MayAugust 13,12, 2026, the LACWarrants Warrant and the JV Warrant havehad not been exercised.

Reworded

Periodic repayments of principal and interest on the DOE Loan commence January 20, 2029.2029, The DOE Loanwhich has a maturity date of July 20, 2048. ThePrepayment Companyis may prepay the loanpermitted at any time, subject to certain conditions, by paying principal plus accrued interest on outstanding advances.conditions.

Reworded

TheAs of June 30, 2026, the Company received itsadvances first advance onunder the DOE Loan of $435.0 million on October 20, 2025 and its second advance on the DOE Loan of2025, $432.0 million on February 24, 2026, and $342.0 million on June 3, 2026.

Reworded

On October 15, 2024, the Company entered into an investment agreement (the “Investment Agreement”) with GM to establish a JV for the purpose of funding, developing, constructing and operating Thacker Pass (the “JV Transaction”). Prior to closing theThe JV Transaction closed on December 23, 2024, prior to which the Company transferred its interest and certain other assets into Lithium Nevada Ventures. InUnder connectionthe withInvestment Agreement, GM acquired a 38% asset-level ownership stake in Thacker Pass for $625.0 million in total cash and letters of credit, including $430.0 million of direct cash funding to the JV Transaction,for Phase 1 construction and a $195.0 million letter of credit facility (“LC Facility”) for DOE Loan reserve account collateral (issued for the Companybenefit alsoof closedCitibank, anN.A. amendmentin toits capacity as collateral agent under the DOE Loan on DecemberAugust 20,5, 2024 to accommodate changes relating to the JV Transaction.2025).

Removed

Under the terms of the Investment Agreement, GM acquired a 38% asset-level ownership stake in Thacker Pass for $625.0 million in total cash and letters of credit, including $430.0 million of direct cash funding to the JV to support the construction of Phase 1 and a $195.0 million letter of credit facility (“LC Facility”) that can be used as collateral to support reserve account requirements under the DOE Loan. On August 5, 2025, the $195.0 million LC Facility was released by GM to LN.

Reworded

Pursuant to an offtake agreement, GM is required to purchase lithium production from Thacker Pass Phase 1, equal to 20% of GM’s specific lithium requirements, up to 100% of Phase 1 production volume (“Phase 1 Offtake Agreement”). Concurrently with closing of the DOE Loan, the Phase 1 Offtake Agreement was, extended to 20 years.years Asconcurrently part ofwith the JVDOE Transaction,Loan closing. GM also entered into an additional 20-year offtake agreement for up to 38% of production volumes from Phase 2 of Thacker Pass and retained its right of first offer on the remaining balance of Phase 2 volumes (“Phase 2 Offtake Agreement” and, together with the Phase 1 Offtake Agreement, the “Offtake Agreements”)., retaining a right of first offer on the remaining Phase 2 balance.

Added

On October 7, 2025, in connection with the OWCA, the Company and GM agreed to amend the Offtake Agreements to, among other things, accelerate delivery dates for annual forecasts, extend the initial forecast period from two to three years (with the second and third years non-binding), require the JV to prioritize GM’s volume requirements, cap third-party commitments based on the difference between production and purchase forecasts, cap GM’s forecast growth at 20% year-over-year during the first five years, and provide GM with a profit true-up right if relinquished volumes are later needed at higher third-party costs.

Showing the first 60 of 128 changed paragraphs. The complete comparison will be part of Pro (coming soon). Meanwhile you can read the full text in the original filing.

LAC insider buying and selling (Form 4)

Since 2026-04-11, insiders reported open-market purchases in 0 Form 4 filings and open-market sales in 1 filing (1 insider, 1 trade date, 6,342 shares, about $28.5K). Net open-market shares: -6,342 (purchases minus sales); net value about -$28.5K.Totals add up every open-market (code P and S) line in those filings, using the prices reported in the filings. Awards, option exercises, tax withholding and gifts are listed below but not counted.

Trade dateInsiderTransactionSharesPriceValueOwned afterFiling
2026-06-26Montgomery Philip
Director
Option exercise 19,348— —19,348 SEC
2026-06-15Grandy Edward
Sr VP, GC & Secretary
Shares withheld for tax 15$4.45 $67173,307 SEC
2026-04-10Dushnisky Kelvin Paul Michael
Director, EVP, Capital Projects
Shares withheld for tax 42,040$4.17 $175.3K210,504 SEC
2026-04-10Zawadzki Alexi Illya
VP, Resource Development
Option exercise 17,712— —124,039 SEC
2026-04-10Zawadzki Alexi Illya
VP, Resource Development
Shares withheld for tax 27,806$4.13 $114.8K96,233 SEC
2026-04-10Russell-Smith Robert
SVP, Finance
Shares withheld for tax 2,379$4.13 $9.8K1,844 SEC
2026-04-10Grandy Edward
Sr VP, GC & Secretary
Shares withheld for tax 25,590$4.17 $106.7K173,322 SEC
2026-04-10Grandy Edward
Sr VP, GC & Secretary
Option exercise 21,218— —198,912 SEC
2026-04-10Gerspacher Richard
EVP, Capital Projects
Shares withheld for tax 37,267$4.17 $155.4K146,838 SEC
2026-04-10Gerspacher Richard
EVP, Capital Projects
Option exercise 34,239— —184,105 SEC
2026-04-10Evans Jonathan David
Director, President & CEO
Shares withheld for tax 85,296$4.17 $355.7K781,445 SEC
2026-04-10Evans Jonathan David
Director, President & CEO
Option exercise 97,897— —866,741 SEC
2026-04-10Crowley Timothy Ambrose
SVP Government & Ext. Affairs
Option exercise 15,673— —181,011 SEC
2026-04-10Colton Luke
EVP & Chief Financial Officer
Option exercise 39,183— —76,737 SEC
2026-04-10Colton Luke
EVP & Chief Financial Officer
Shares withheld for tax 26,452$4.17 $110.3K50,285 SEC
2026-04-10Barnum Aubree
VP, Human Resources
Option exercise 15,673— —116,372 SEC
2026-04-10Barnum Aubree
VP, Human Resources
Shares withheld for tax 17,278$4.17 $72.0K99,094 SEC
2025-11-17Grandy Edward
Sr VP, GC & Secretary
Open-market sale 6,342$4.50 $28.5K135,306 SEC