Largest changes
“In November 2018, the ACC voted to re-examine the facilitation of a deregulated retail electric market in Arizona. On July 1 and July 2, 2019, ACC Staff issued a report and initial proposed draft rules regarding possible modifications to the ACC’s retail electric competition rules. On February 10, 2020, two ACC Commissioners filed two sets of draft proposed retail electric competition rules. On February 12, 2020, ACC Staff issued its second report regarding possible modifications to the ACC’s retail electric competition rules. …”see in full comparison
“Modification of the ACC’s retail electric competition rules or other efforts of deregulation and other factors, such as customers installing behind the meter technologies or large customers developing large, utility scale generation projects to serve their energy needs, may result increased competition, which could have a significant adverse impact on APS’s business and results of operations.”see in full comparison
“Longer term, APS has been preparing for and can serve significant load growth from residential and business customers. On top of these existing growth trends, APS is also now receiving unprecedented incremental requests for service from extra-large commercial energy users (over 25 MW) with very high energy demands that persist virtually around-the-clock. These incremental requests for service by extra-large energy users far exceed available generation and transmission resource capacity in the Southwest region for the foreseeable future. …”see in full comparison
“Recent industry trends and projections of load growth reflect significant demand from data centers to support AI as well as onshoring of manufacturing, such as advanced semiconductor manufacturing. These data centers and large manufacturers may locate their operations within service territories other than our own. If they do choose to locate within our service territory, we may not be able to provide sufficient electric service within the time period they require due to capital or other constraints. …”see in full comparison
“Additionally, as APS’s transmission infrastructure ages and its transmission system needs grow to support growth in our territory and in the Southwest, it will need to replace and expand certain portions of its transmission infrastructure, which requires significant investment of capital. Risks related to the timely completion of, and costs associated with, these projects may be exacerbated by a constrained supply chain limiting the availability of necessary parts and materials as well as APS’s use, in some cases, of older, obsolete, or unsupported equipment. …”see in full comparison
“Additionally, as APS’s transmission infrastructure ages and its transmission system needs to grow to support growth in our territory and in the Southwest, it will need to replace and expand certain portions of its transmission infrastructure, which requires significant investment of capital. Risks related to the timely completion of, and costs associated with, these projects may be exacerbated by a constrained supply chain limiting the availability of necessary parts and materials as well as APS’s use, in some cases, of older, obsolete, or unsupported equipment. …”see in full comparison
Full comparison: every changed paragraph (33)
The ACC must also approve APS’s issuance of equity and debt securities,securities and any significant transfer or encumbrance of APS property used to provide retail electric service and must approve or receive prior notification of certain transactions between us, APS, and our respective affiliates, including the infusion of equity into APS. Decisions made by the ACC or FERC could have a material adverse impact on our financial condition, results of operations, or cash flows.
APS must comply in good faith with all applicable statutes, regulations, rules, tariffs, executive orders and orders of agencies that regulate APS’s business, including FERC, NRC, EPA, the ACC, and state and local governmental agencies. These laws, regulations, and agencies regulate many aspects of APS’s utility operations, including safety and performance, emissions, siting and construction of facilities, labor and employment, customer service and the rates that APS can charge retail and wholesale customers. Failure to comply can subject APS to, among other things, fines and penalties. For example, under the Energy Policy Act of 2005, FERC can impose penalties (approximately $1.2 million per day per violation) for failure to comply with mandatory electric reliability standards. APS is also required to have numerous permits, approvals and certificates from these agencies. APS believes the necessary permits, approvals and certificates have been obtained for its existing operations and that APS’s business is conducted in accordance with applicable laws in all material respects.
Environmental Clean Up. APS has been named as a PRP for Superfund sites in Phoenix, Arizona, and it could be named a PRP in the future for other environmental clean-up at sites identified by a regulatory body. APS cannot predict with certainty the amount and timing of all future expenditures related to environmental matters because of the difficulty of estimating clean-up costs. There is also uncertainty in quantifying liabilities under environmental laws that impose joint and several liability on all PRPs.
Coal Ash. In December 2014, the EPA issued final regulations governing the handling and disposal of CCR, which are generated as a result of burning coal and consist of, among other things, fly ash and bottom ash. The rule regulates CCR as a non-hazardous waste. APS disposes of CCR in ash ponds and dry storage areas. To the extent the rule requires the closure or modification of these CCR units, modification or changes to the manner of closure of such units, or the construction of new CCR units beyond what we currently anticipate, APS would incur significant additional costs for CCR disposal. In addition, the rule may also require corrective action to address releases from CCR disposal units or the presence of CCR constituents within groundwater near CCR disposal units above certain regulatory thresholds.
Ozone National Ambient Air Quality Standards. In 2015, the EPA finalized revisions to the NAAQS for ozone, which set new, more stringent standards on emissions of nitrogen oxide, a precursor to ozone, in an effort to protect human health and human welfare. Depending on the final attainment designations for the new standards and the state implementation requirements, APS may be required to invest in new pollution control technologies and to generate emission offsets for new projects or facility expansions located in ozone nonattainment areas. In addition, the EPA may in the future further increase the stringency of various NAAQS, including for ozone or other pollutants, such as particulate matter. With regard to even more stringent NAAQS requirements, additional control measures and compliance costs may become necessary for APS as well as its current and potential future customers.
See “Business of Arizona Public Service Company — Environmental Matters” in Part I, Item 1 as well as Note 14 for examples of environmental laws and regulations and matters that could affect APS’s financial condition, results of operations and cash flows.
Concern over climate change has led to significant legislative and regulatory efforts to limit CO2,carbon dioxide, which is a major byproduct of the combustion of fossil fuel, and other GHG emissions.
Potential Financial Risks — Greenhouse GasGHG Regulation, the Clean Power Plan and Potential Litigation. On April 25, 2024, the EPA issued new GHG emission standards for power plants. These new standards are focused on limiting power plant GHG emissions through control mechanisms that can be implemented at individual power plant facilities. The new regulations are currently being challenged in federal court.court and, in 2025, EPA proposed a rule to repeal these GHG emission standards. Additionally, the Trump administration has stated that it intends to reverse or substantially revise these standards. See Item“Business 1of -Arizona Public Service Company — Environmental Matters -— Climate Change” in Part I, Item 1 for more information.
APS owns certain of its power plants and transmission facilities jointly with other owners, with varying ownership interests in such facilities. Changes in the nature of our industry and the economic viability of certain plants and facilities, including impacts resulting from types and availability of other resources, fuel costs, legislation, and regulation, together with timing considerations related to the expiration of leases or other agreements for such facilities, could result in unaligned positions among co-owners. Differences in the co-owners’ willingness or ability to continue their participation could lead to the eventual shut down of units or facilities and uncertainty related to the resulting cost recovery of such assets. See Note 38 for a discussion of the Navajo Plant and Cholla retirementretirements and the related risks associated with APS’s continued recovery of its remaining investment in the plant.
Deregulation or restructuring of the electric industry and other factors may result in increased competition, which could have a significant adverse impact on APS’s business and its results of operations.
Modification of the ACC’s retail electric competition rules or other efforts of deregulation and other factors, such as customers installing behind the meter technologies or large customers developing large, utility scale generation projects to serve their energy needs, may result increased competition, which could have a significant adverse impact on APS’s business and results of operations.
In November 2018, the ACC voted to re-examine the facilitation of a deregulated retail electric market in Arizona. On July 1 and July 2, 2019, ACC Staff issued a report and initial proposed draft rules regarding possible modifications to the ACC’s retail electric competition rules. On February 10, 2020, two ACC Commissioners filed two sets of draft proposed retail electric competition rules. On February 12, 2020, ACC Staff issued its second report regarding possible modifications to the ACC’s retail electric competition rules. During a July 15, 2020, ACC Staff meeting, the ACC Commissioners discussed the possible development of a retail competition pilot program, but no action was taken. The ACC continues to discuss matters related to retail electric competition, including the potential for additional buy-through programs or other pilot programs. In April 2022, the Arizona Legislature passed, and the Governor signed, a bill that repealed the electric deregulation law that had been in place in Arizona since 1998. On August 27, 2024, the ACC administratively closed this docket due to inactivity and obsolescence. Modification of the ACC’s retail electric competition rules or other efforts of deregulation could result in increased competition, which could have a significant adverse impact on APS’s business and results of operations.
Effects of Energy Conservation Measures and Distributed Energy Resources. APS customers participate in energy efficiency and conservation programs and other demand-side managementDSM efforts, which in turn impact the demand for electricity. APS must also meet certain distributed renewable energy requirements. A portion of APS’s total renewable energy requirement must be met with an increasing percentage of distributed renewable energy resources (generally, small-scale renewable technologies located on customers’ properties). The distributed renewable energy requirement is 30% of the applicable RES requirement for 2012 and subsequent years (APS requestedwas granted a waiver of this requirement in theits 2024 and 20252026 RES Implementation Plans, which have not yet been approved by the ACCPlan). Customer participation in distributed renewable energy programs would result in lower demand since customers would be meeting some of their own energy needs.
Actual and Projected Customer and Sales Growth. APS’s actualActual sales growth, excluding weather-related variations, may differ from itsour projections as a result of numerous factors, such as economicmacroeconomic conditions, current and future economic, regulatory, business, and other conditions, such as the Arizona housing market, customer growth, the legal, regulatory, and business environment in Arizona, usage patterns and energy conservation, slower than expected ramp-up of and/or fewer than expectedlarge data centers and large manufacturing facilities, slower than expected commercial and industrial expansions, impacts of energy efficiency programs and growth in DG, responses to retail price changes, changes in regulatory standards, and impacts of new and existing laws and regulations, including environmental laws and regulations. Based on past experience, a 1% variation in our annual residential and small commercial and industrial kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $24$25 million, and a 1% variation in our annual large commercial and industrial kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $6$7 million.
Recent industry trends and projections of load growth reflect significant demand from data centers to support AI as well as onshoring of manufacturing, such as advanced semiconductor manufacturing. These data centers and large manufacturers may locate their operations within service territories other than our own. If they do choose to locate within our service territory, we may not be able to provide sufficient electric service within the time period they require due to capital or other constraints. APS may need to accelerate development plans of the related generation and transmission facilities to serve these potential customers, which may necessitate alternative financing structures, such as the novel subscription model we are pursuing in an effort to ensure growth pays for growth and reduce cross-subsidization of customer classes, as well as ACC approval. APS may not be able to secure facilities or regulatory approval to support these customers in a timely manner. Additionally, the future demand from these customers may not be realized to the extent currently projected and significant uncertainties exist regarding the future energy demand associated with data centers and AI. The difficulty in forecasting these demands and the additional risk of these arrangements could lead to stranded costs and other effects that could have material adverse impacts on APS’s financial condition, results of operations, and cash flows.
Longer term, APS has been preparing for and can serve significant load growth from residential and business customers. On top of these existing growth trends, APS is also now receiving unprecedented incremental requests for service from extra-large commercial energy users (over 25 MW) with very high energy demands that persist virtually around-the-clock. These incremental requests for service by extra-large energy users far exceed available generation and transmission resource capacity in the Southwest region for the foreseeable future. APS is exploring available options for securing sufficient electric generation and transmission to meet these projections of future customer needs; however, there are difficulties in properly forecasting the demands of these extra-large customers due to factors such as the nascent nature of the industries (e.g., artificial intelligence) that these customers are supporting and the multiple variables that impact their usage ramp-up and ultimate level of demand. As data center and other extra-large customer opportunities evolve and develop, we may also enter into arrangements with customers and potential customers that require us to invest capital and assume credit risk related to such developments and the related generation and transmission investments before we receive any potential return. APS is implementing strategies to attempt to reduce this risk; however, the difficulty in forecasting these demands and the additional risk of these arrangements could lead to stranded costs and other effects that could have material adverse impacts on APS’s financial condition, results of operations, and cash flows.
The operation of power generation, transmission and distribution facilities involves certain risks, including the risk of breakdown or failure of equipment, fuel interruption, and performance below expected levels of output or efficiency. Unscheduled outages, including extensions of scheduled outages due to mechanical failures or other complications, occur from time to time and are an inherent risk of APS’s business. Because our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by unexpected or uncontrollable events occurring on the larger transmission power grid, and the operation or failure of our facilities could adversely affect the operations of others. Concerns over the physical security of these assets could include damage to certain of our facilities due to vandalism or other deliberate acts that could lead to outages or other adverse effects. If APS’s facilities operate below expectations, especially during its peak seasons, it may lose revenue or incur additional expenses, including increased purchased power expenses.
Additionally, as APS’s transmission infrastructure ages and its transmission system needs grow to support growth in our territory and in the Southwest, it will need to replace and expand certain portions of its transmission infrastructure, which requires significant investment of capital. Risks related to the timely completion of, and costs associated with, these projects may be exacerbated by a constrained supply chain limiting the availability of necessary parts and materials as well as APS’s use, in some cases, of older, obsolete, or unsupported equipment. Certain replacements and expansions of the transmission infrastructure will also require the acquisition or renewal of land leases, easements, or other rights-of-way that may require approvals from landowners, including individuals, governmental agencies, and, at times, tribal nations. APS is unable to predict the outcomes of any pending or future required approvals, including any related costs, which could be significant. If APS is unable to successfully manage the replacement and expansion of its transmission infrastructure, it could face increased equipment failures, power quality challenges, reputational impact, and financial loss.
The operation of power generation, transmission and distribution facilities involves certain risks, including the risk of breakdown or failure of equipment, fuel interruption, and performance below expected levels of output or efficiency. Unscheduled outages, including extensions of scheduled outages due to mechanical failures or other complications, occur from time to time and are an inherent risk of APS’s business. Because our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by unexpected or uncontrollable events occurring on the larger transmission power grid, and the operation or failure of our facilities could adversely affect the operations of others. Concerns over the physical security of these assets could include damage to certain of our facilities due to vandalism or other deliberate acts that could lead to outages or other adverse effects. If APS’s facilities operate below expectations, especially during its peak season, it may lose revenue or incur additional expenses, including increased purchased power expenses.
Additionally, as APS’s transmission infrastructure ages and its transmission system needs to grow to support growth in our territory and in the Southwest, it will need to replace and expand certain portions of its transmission infrastructure, which requires significant investment of capital. Risks related to the timely completion of, and costs associated with, these projects may be exacerbated by a constrained supply chain limiting the availability of necessary parts and materials as well as APS’s use, in some cases, of older, obsolete, or unsupported equipment. Certain replacements and expansions of the transmission infrastructure will also require the acquisition or renewal of land leases, easements, or other rights-of-way that may require approvals from landowners, including individuals, government agencies, and, at times, tribal nations. APS is unable to predict the outcomes of any pending or future required approvals, including any related costs, which could be significant. If APS is unable to successfully manage the replacement and expansion of its transmission infrastructure, it could face increased equipment failures, power quality challenges, reputational impact, and financial loss.
The inability to successfully develop, acquire or operate generation resourcesand transmission facilities to meet future resource needs and load forecasts in accordance with reliability requirements and other new or evolving standards and regulations could adversely impact our business.
Potential changes in regulatory standards, impacts of new and existing laws and regulations, including environmental laws and regulations, and the need to obtain various regulatory approvals create uncertainty surrounding our current and future generation portfolio. TheCurrent current regulatory standards, laws,laws and regulations as well as changes to those laws and regulations, including via judicial decisions and executive orders, create strategic challenges asin toacquiring thean appropriate generation portfolio and fuel diversification mix. In addition, APS is required by the ACC to meet certain energy resource portfolio requirements, including those related to renewables development and energy efficiency measures, in addition to specific competitive resource procurement requirements. Operating, maintaining, and developing our generation and other assets requires significant capital expenditures and operations and maintenance costs that may be difficult to maintain at adequate levels while maintaining reliability. The development and operation of anythese generation facilityfacilities is also subject to manyother risks, including those related to financing, siting, permitting, new and evolving technology, extreme weather events, workforce issues, cybersecurity attacks, supply chain constraints for key equipment and critical spare parts, overreliance on or the existence of a small number of suppliers, access to fuel, and the construction of sufficient transmission capacity to support these facilities among others. Macroeconomic and geopolitical factors may also impact our ability to procure the generation and other equipment we need to meet customer demand. APS needs to develop or acquire new generation and other facilities, potentially modernize existing facilities, and/or contract for additional capacity in order to meet future resource needs and load forecasts. APS’s inability to do so could have a material adverse impact on our business and results of operations.
In JanuaryAugust 2020,2025, APS announced an update to its clean energy goal from zero-carbon to provide 100% clean, carbon-free electricitycarbon-neutral by 2050 with an intermediate 2030 target of achieving a resource mix that is 65% clean energy, with 45% of the generation portfolio coming from renewable energy.2050. APS’s ability to successfully execute its clean energy commitmentgoal is dependent upon a number of external factors, some of which include supportive national and state energy policies, a supportive regulatory environment, sales and customer growth, the development, deployment and advancement of clean energy technologies, adequate supply chain for generation resources, and continued access to capital markets.
Assured supplies of water are important for APS’s generating plants. Water in the southwestern United States is limited, and various parties have made conflicting claims regarding the right to access and use such limited supplies of water. Both groundwater and surface water in areas important to the operation of APS’s generating plants have been and are the subject of inquiries, claims and legal proceedings. In addition, the region in which APS’s power plants are located suffers from prolonged drought conditions, which could potentially affect the plants’ water supplies. Climate change is also projected to exacerbate such drought conditions. In addition, Colorado River water supplies for Arizona are subject to a Tier 1 shortage declaration,declarations whichthat substantially limitslimit the quantity of water available to the state. Due to stressed surface water and groundwater supplies, there is focus on the increased use of treated effluent to supplement statewide water supplies, which could increase competition for the state.treated effluent that some APS generating plants rely on. APS’s inability to access sufficient supplies of water, along with that of its customers, could have a material adverse impact on our business and results of operations.
We are subject to cybersecurityrisk risksrelated to cybersecurity, IT systems, and risks of unauthorized access to our systems that could adversely affect our business and financial condition.
We rely extensively on IT systems, networks, and services, including internet sites, data hosting and processing facilities, and other hardware, software and technical applications and platforms. Some of these systems are managed, hosted, provided, or used by third parties to assist in conducting our business.
We rely extensively on IT systems, networks, and services, including internet sites, data hosting and processing facilities, and other hardware, software and technical applications and platforms. Some of these systems are managed, hosted, provided, or used by third parties to assist in conducting our business. Malicious actors may attack vendors to disrupt the services these vendors provide to us or to use those vendors as a cyber conduit to attack us. As more third parties are involved in the operation of our business, there is a risk the confidentiality, integrity, privacy, or security of data held by, or accessible to, third parties may be compromised. In addition to the involvement of third parties and the associated security risks, we also face risks when integrating new IT systems, such as those associated with costs, operational efficiency, and security compliance. Our IT systems introduce layers of execution complexity and resource risks across the entire organization.
If a significant cybersecurity event or breach were to occur, we may not be able to fulfill critical business functions and we could (i) experience property damage, disruptions to our business, theft of or unauthorized access to customer, employee, financial or system operation information or other information; (ii) experience loss of revenue or incur significant costs for repair, remediation and breach notification, and increased capital and operating costs to implement increased security measures; and (iii) be subject to increased regulation, litigation and reputational damage. If such disruptions or breaches are not detected quickly, their effects could be compounded or could delay our response or the effectiveness of our response and ability to limit our exposure to potential liability. These types of events wouldas well as the impacts of integrating new IT systems could also require significant management attention and resources and could have a material adverse impact on our financial condition, results of operations, or cash flows.
APS has an ownership interest in and operates on behalf of a group of participants, Palo Verde, which is the largest nuclear electric generating facility in the western United States. Palo Verde constitutes approximately 18% of APS’s owned and leased generation capacity. Palo Verde is subject to environmental, health and financial risks, such as the ability to obtain adequate supplies of nuclear fuel; the ability to dispose of spent nuclear fuel; the ability to maintain adequate reserves for decommissioning; potential liabilities arising out of the operation of these facilities; the costs of securing the facilities against possible terrorist attacks; and unscheduled outages due to equipment and other problems. APS maintains nuclear decommissioning trust funds and external insurance coverage to minimize its financial exposure to some of these risks; however, it is possible that damages could exceed the amount of insurance coverage. APS may be required under federal law to pay up to $144.9 million (but not more than $21.6 million per year) of liabilities arising out of a nuclear incident not only at Palo Verde, but at any other nuclear power plant in the United States. In addition, APS is subject to retrospective premium adjustments under its nuclear property insurance policies with Nuclear Electric Insurance Limited (“NEIL”) for approximately $23.1$24.2 million if NEIL’s losses in any policy year exceed accumulated funds and if the retrospective premium assessment is declared by NEIL’s Board of Directors. Although APS has no reason to anticipate a serious nuclear incident at Palo Verde, if an incident did occur, it could materially and adversely affect our results of operations and financial condition. A major incident at a nuclear facility anywhere in the world could cause the NRC to limit or prohibit the operation or licensing of any domestic nuclear unit and to promulgate new regulations that could require significant capital expenditures and/or increase operating costs.
Our current ratings are set forth in “Liquidity and Capital Resources — Credit Ratings” in Part II, Item 7. We cannot be sure that any of our current ratings will remain in effect for any given period of time or that a rating will not be lowered or withdrawn entirely by a rating agency if, in its judgment, circumstances in the future so warrant. Any downgrade or withdrawal could adversely affect the market price of Pinnacle West’s and APS’s securities, limit our access to capital and increase our borrowing costs, which would adversely impact our financial results. We could be required to pay a higher interest rate for future financings, and our potential pool of investors and funding sources could decrease. In addition, borrowing costs under our existing credit facilities depend on our credit ratings. A downgrade could also require us to provide additional support in the form of letters of credit or cash or other collateral to various counterparties. If our short-term ratings were to be lowered, it could severely limit access to the commercial paper market. We note that the ratings from rating agencies are not recommendations to buy, sell or hold our securities and that each rating should be evaluated independently of any other rating.
Investment performance, changing interest rates, new rules or regulations and other economic, social, and political factors could decrease the value of our benefit plan assets, nuclear decommissioning trust funds and other special use funds or increase the valuation of our related obligations, resulting in significant additional funding requirements. We are also subject to risks related to the provision of employee healthcare benefits and healthcare reform legislation. Any inability to fully recover these costs in our utility rates would negatively impact our financial condition.
Pending or future federal or state legislative or regulatory activity or court proceedings could increase the costs of providing medical insurance for our employees and retirees. Any potential changes and resulting cost impacts cannot be determined with certainty at this time.
General economic factors that are beyond the Company’s control impact the Company’s forecasts and actual performance. These factors include interest rates; recession; inflation; stagflation; deflation; supply chain constraints; unemployment trends; sanctions, trade restrictions, military interventions and the threat or possibility of war; terrorism or other global or national unrest; and political or financial instability. In particular, in recent years the United States’ economy experienced a substantial rise in the inflation rate and more recently in 2025,2025 the Trump administration has implemented tariffs and discussed additional tariffs, which would further increase costs. The Company is currently evaluating the impact of the recent U.S. Supreme Court’s decision regarding the validity of certain tariffs previously imposed under the International Emergency Powers Act, including whether any or all of the tariffs will be eligible for a refund as well as the potential for replacement tariffs under separate statutory authorities. Additionally, supply chains have been impacted and could be further impacted by inflation, tariffs, and other sociopolitical factors, resulting in equipment delays and increased costs. AAny failure to recover these potential increased costs through our rates could have a material adverse impact on our financial condition, results of operations, or cash flows.
Management's Discussion & Analysis (MD&A)
New heading “Resource Planning—Prioritizing Reliability and Affordability”
New heading “APS Consolidated”
Removed heading “Clean Energy Commitment”
Removed heading “New Nuclear Generation”
Removed heading “Electric Vehicles”
Removed heading “Sustainability Practices”
Removed heading “Artificial Intelligence”
Removed heading “Fire Mitigation”
Removed heading “Inflation Reduction Act of 2022”
Largest changes
“We are committed to keeping bills as low as possible for our customers while maintaining high levels of reliability. Inflation has dramatically impacted the cost of goods and services in recent years as shown by the Consumer Price Index for All Urban Consumers (“CPI-U”), which from 2018 through 2024 rose nationally 24.9% and 32.1% in Phoenix. Despite this, APS’s average residential rates remained well-below those inflation figures, rising 16.2% for the same period according to the U.S. Energy Information Administration. …”see in full comparison
All of Pinnacle West’ssee in full comparisonloanand APS’s credit agreements contain “cross-default” provisions that would result in defaults and the potential acceleration of paymentunder these loan agreementsif Pinnacle West orAPS were to default under certain other material agreements. All of APS’s bank agreements contain “cross-default” provisions that would result in defaults and the potential acceleration of payment under these bank agreements ifAPS were to default under certain other material agreements. Pinnacle West and APS do not have a material adverse changerestrictioncovenant for credit facility borrowings.
“APS continues to focus on mitigating the cost pressures related to inflation and other factors, such as tariffs. Overall inflation grew by 1.6% in Phoenix and 2.9% nationally over the twelve months ended December 2024. Although inflationary impacts to APS began to slow in 2024, APS is still managing the impacts high inflation. Additionally, the implementation of recent and future tariffs could further escalate costs and introduce supply chain constraints.”see in full comparison
“Artificial Intelligence. To address the rapid advancement of AI technology risks and opportunities, APS has developed an AI strategy to responsibly utilize AI to advance our business strategy, enhance customer and employee experiences, and optimize operational reliability. At the core of our AI strategy is a robust governance model that develops guidance, policies, and relevant sub-strategies for the execution of AI projects at the Company. …”see in full comparison
The ratings of securities of Pinnacle West and APS as of Februarysee in full comparison18,20,2025,2026, are shown below. We are disclosing these credit ratings to enhance understanding of our cost of short-term and long-term capital and our ability to access the markets for liquidity and long-term debt. The ratings reflect the respective views of the rating agencies, from which an explanation of the significance of their ratings may be obtained. There is no assurance that these ratings will continue for any given period. The ratings may be revised or withdrawn entirely by the rating agencies if, in their respective judgments, circumstances so warrant. Any downward revision or withdrawal may adversely affect the market price of Pinnacle West’s or APS’s securities and/or result in an increase in the cost of, or limit access to, capital. Such revisions may also result in substantial additional cash or other collateral requirements related to certain derivative instruments, insurance policies, natural gas transportation, fuel supply, and other energy-related contracts.On March 7, 2024, S&P affirmed the ratings and revised Pinnacle West’s and APS’s outlooks from negative to stable. On March 20, 2024, Moody’s downgraded both Pinnacle West’s and APS’s credit ratings by a notch and revised their outlooks from negative to stable. On March 26, 2024, Fitch affirmed APS’s ratings and downgraded Pinnacle West’s ratings by a notch. Fitch revised the outlook for both Pinnacle West and APS from negative to stable.At this time, we believe we have sufficient available liquidity resources to respond to a potential downward revision to our credit ratings.
“In 2024, the Sustainability Department engaged an external consultant and leveraged input from employees, large customers, limited-income advocates, economic development groups, tribes, nonprofits, environmental non-governmental organizations, residential customers, and other stakeholders to identify and assess the sustainability issues that matter most. In total, 15 Priority Sustainability Issues (“PSIs”) were identified and prioritized. …”see in full comparison
Full comparison: every changed paragraph (199)
Pinnacle West is an investor-owned electric utility holding company based in Phoenix, Arizona with consolidated assets of approximately $26 billion. Since 1886, Pinnacle West and our affiliates have provided energy and energy-related products to people and businesses throughout Arizona.
Pinnacle West derivesis an investor-owned electric utility holding company based in Phoenix, Arizona with consolidated assets of approximately $30 billion. We derive essentially all of our revenues and earnings from our principal subsidiary, APS. Since 1886, APS and its affiliates have provided energy and energy-related products to people and businesses throughout Arizona. APS is Arizona’s largest and longest-serving electric company thatand generates safe, affordable and reliable electricity for approximately 1.4 million retail customers in 11 of Arizona’s 15 counties. APS is also the operator and co-owner of Palo Verde — a primary source of electricity for the southwestern United States. Our other active subsidiaries are El Dorado and PNW Power.
Our vision is to create a sustainable energy future for Arizona. Our mission is to serve customers with safe, reliable, and affordable energy. We are committed to delivering operational excellence at the lowest cost possible while aspiring to lower carbon emissions over time.
As energy demand in Arizona continues to grow, we remain committed to delivering reliable service to our customers. We have a goal of achieving top quartile reliability as compared to peers. Key elements to delivering reliable service include resource and transmission planning to secure resource adequacy, planning and procuring resources to ensure sufficient reserve margins, distribution automation and resiliency investments, predictive and preventative maintenance programs, seasonal readiness programs, emergency preparedness, and securing a reliable supply chain. Securing a reliable grid requires ongoing infrastructure investments in addition to investments to support new customer growth.
Balanced Energy Mix. APS strives to procure a balanced energy mix, and we believe this provides the greatest reliability at the lowest cost possible while increasing resiliency. We achieve reliability, in part, through a blend of dispatchable resources, such as natural gas and battery storage, that can provide energy when intermittent resources, such as wind and solar, are unavailable. APS regularly evaluates the best mix of resources based on a changing operating environment, including changes in generation technology, economics, and policy impacts.
Additional natural gas capacity is necessary to support reliable service and meet increasing energy needs. However, existing natural gas pipelines into Arizona are currently 100% committed. As a result, in July 2025, APS executed a gas transportation precedent agreement to secure a long-term supply of natural gas. The new pipeline is expected to be operational by late 2029 and will be owned and operated by a third-party. See Note 14 for more information. APS also plans to add up to 2,000 MW of flexible natural gas generation to its portfolio, designed to help meet the growing around-the-clock energy needs in Arizona. This generation is expected to serve existing customers and business-as-usual growth through our competitive ASRFP process as well as a new subscription model for large load customers, like data centers and large manufacturers. This subscription model is a commercial construct designed to ensure growth pays for growth while protecting affordability for other customers.
Palo Verde, one of the nation’s largest carbon-free energy resources, serves as a foundational part of APS’s resource portfolio. The plant is a critical asset to the Southwest, generating more than 32 million MWh – enough power for roughly 3.4 million households, or approximately 8.5 million people. Its continued operation is important to a carbon-neutral future for Arizona and the region, as a reliable, continuous, affordable resource and as a large contributor to the local economy. APS owns or leases 29.1% of Units 1, 2, and 3 Palo Verde. In June 2025, APS entered into agreements to purchase two of the three leased interests in Unit 2. The two subject leased interests represented approximately 7% or 94 MW of Unit 2. The transaction closed in September 2025, leaving one remaining lease for approximately 5.2% of Unit 2 that expires in 2033. See Note 12 for more information. APS’s rate case application filed in 2025 (the “2025 Rate Case”) includes pro forma adjustments to account for these acquisitions. APS continues to evaluate and pursue options for reliably serving growing customer energy needs and demand.
Wildfire Efforts. Wildfire safety remains a critical focus for APS and other utilities. APS has increased investment in fire mitigation efforts to clear defensible space around its infrastructure, continue ongoing system upgrades, build partnerships with government entities and first responders, and educate customers and communities. APS also increased spend on mitigating the risk associated with trees that could cause hazards, resulting in more of these trees being removed before they could cause outages or wildfires. These programs contribute to customer reliability, responsible forest management and safe communities. With wildfire events in Hawaii, California, and across North America over the last few years, APS has been devoting and intends to continue to devote substantial efforts to analyzing and developing enhancements to its systems and processes to mitigate fire risk within its service territory and communities, including by hardening our infrastructure, deploying new technologies where appropriate, increasing our awareness, implementing operational changes, and enhancing our wildfire response capabilities.
APS uses fire modeling software to identify and calculate risk and target future system improvement investments such as fire-resistant pole wrapping, wood to steel pole conversions, and additional remote-controllable field devices like reclosers and switches. In 2024, APS began installing a system of artificial intelligence-based fire sensing cameras with the ability to detect and alert on fire ignitions. These alerts are sent both to APS and fire response dispatch centers to speed fire response in APS’s service territory regardless of the cause of the fire. APS also implemented a public safety power shutoff (“PSPS”) program on certain feeders that began in the 2024 fire season, leveraging the additional real-time analysis provided by the modeling software. APS has educated and will continue education outreach to customers and communities that may potentially be impacted by the PSPS program.
APS was selected by DOE’s Grid Deployment Office (“GDO”) to receive up to $70 million in federal money for fire mitigation and grid infrastructure projects. This funding is part of the GDO’s Grid Resilience and Innovation Partnership Program and is contingent on APS negotiating and executing final grant agreements with GDO. Additionally, on May 12, 2025, Arizona Governor Hobbs signed into law a bill that requires Arizona electric utilities to develop and seek approval for wildfire mitigation plans and defines the standard of care with respect to wildfire-related claims by reference to such plans. APS continues to evaluate policy and regulatory options, as well as insurance programs, to mitigate the impact of wildfire events.
We are committed to keeping bills as low as possible for our customers while maintaining high levels of reliability. Inflation has dramatically impacted the cost of goods and services in recent years as shown by the Consumer Price Index for All Urban Consumers (“CPI-U”), which from 2018 through 2024 rose nationally 24.9% and 32.1% in Phoenix. Despite this, APS’s average residential rates remained well-below those inflation figures, rising 16.2% for the same period according to the U.S. Energy Information Administration. Inflation has moderated from earlier highs, with CPI-U rising 2.7% nationally and 2.2% in Phoenix over the 12 months ended December 2025. As a result of increased tariffs and supply chain constraints, APS amended several of its agreements from its ASRFP issued in 2023 to mitigate these cost impacts. However, APS remains cautious of potential price increases as a result of current and proposed tariffs, which could lead to higher costs and supply chain constraints, while also monitoring the outcome of the recent U.S. Supreme Court’s decision regarding the validity of certain tariffs.
APS’s customer affordability initiative includes internal opportunities, such as training and mentoring employees on identifying efficiency opportunities; maintaining inventory to take advantage of lower pricing and avoid expediting fees; entering into long-term contracts to hedge against price volatility, which has allowed APS to mitigate against procurement spend on critical items such as transformers; and implementing automation technologies to enhance efficiencies and increase data-oriented decision making. The customer affordability initiative also includes external opportunities, including a portfolio of customer programs designed to help customers reduce and manage their bills. In the 2025 Rate Case, APS is also seeking to reduce cross-subsidization of customer classes and ensure that growth pays for growth by requesting modifications to its cost allocation methodologies. APS continues to seek opportunities to streamline its business processes, mitigate cost increases, increase employee retention, and improve customer satisfaction.
APS’s IRP and competitive ASRFP processes serve important roles in providing reliable and affordable energy to APS’s customers. The IRP process helps identify the amount and type of resources required to reliably meet customer needs, while the ASRFP process seeks to meet those needs in a competitive manner based on cost, ability to meet system requirements, and commercial viability.
APS has seen increasing demand from large load customers in recent years. In the 2025 Rate Case, APS requested adjustments to rate designs and modification of cost allocation methodologies to ensure growth pays for growth. In line with the 2025 Rate Case, APS has developed a subscription model it believes will allow for these large load customers to fund the incremental infrastructure needed to serve them through long-term contracts where they cover capital costs and assume development risks, accelerating their path to service and ensuring those infrastructure costs are borne by those customers rather than residential or small business customers.
There are also external opportunities that allow APS to deliver more affordable energy to customers, such as APS’s participation in western energy markets and programs. APS participated in market design and tariff development of Markets+, a day-ahead and real-time market offering from SPP. The Markets+ tariff was filed with FERC on March 29, 2024 and was approved on January 16, 2025. APS is a funding party to the implementation phase of Markets+ and expects to go live in the market in October 2027. In addition, APS is participating in the Western Resource Adequacy Program administered by Western Power Pool and plans to transition to full-binding participation in 2027 or 2028. These regional efforts are driven by the objectives of reducing customer cost and improving reliability. Until the transition to Markets+, APS will continue to participate in the WEIM as a tool for creating savings for APS’s customers from the real-time only, voluntary market. APS expects that its participation in the WEIM and future participation in Markets+ will lower its fuel and purchased-power costs, improve situational awareness for systems operations in the Western Interconnection, and improve integration of APS’s resources.
Resource Planning—Prioritizing Reliability and Affordability
APS remains focused on providing reliable energy at the lowest cost possible while striving to lower emissions over time and continues to look for opportunities to support reliability through dispatchable resources, such as gas and the potential extension of coal beyond 2031. APS’s diverse portfolio of existing and planned resources includes biomass, biogas, coal, energy storage, geothermal, natural gas, nuclear, solar, and wind. Every three years, APS performs an IRP, a comprehensive study to identify what resources will be necessary to safely, reliably, and affordably meet the demand and energy needs of its customers over the next 15 years. In November 2023, APS released its latest IRP, which identified forecasted customer demand and energy needs growing at an unprecedented rate. In developing the IRP, APS considered how factors such as forecasted economic growth, impacts from weather, and new resource technology availability impact the amount and type of resources required to reliably and affordably meet customer needs. These factors, among others, were used to develop a plan that identified a balanced mix of diverse energy-generating resources to reliably serve customers’ future energy needs. To help ensure competitive costs for resources procured by APS, APS regularly issues competitive bid solicitations through the ASRFP process, with the most recent ASRFP being issued in 2025. These ASRFPs are open to bids for all resource types, including customer-scale (behind the meter) and utility-scale (in front of the meter) resources.
APS selects projects out of ASRFPs based on cost, ability to meet system requirements, and commercial viability, taking into consideration timing and likelihood of successful contracting and development. Guided by IRP-established timelines and quantities, APS maintains a flexible approach that allows it to optimize system reliability and customer affordability through the ASRFP process. Agreements for the development and completion of future resources are subject to various conditions, including successful siting, permitting and interconnection to the electric grid. Consistent with recent ASRFPs, APS remains focused on contracting for resources that can withstand supply chain pressures and volatility and seeks a balanced portfolio that is resilient to other external pressures, including those arising from the macroeconomic and geopolitical environment.
In terms of recent solicitations, APS issued an ASRFP on June 30, 2023, pursuant to which APS procured 3,606 MW of battery storage, 517 MW of natural gas, 2,649 MW of solar, and 500 MW of wind resources expected to be in service from 2026 to 2028. APS issued another ASRFP on November 20, 2024, pursuant to which it signed an amendment and extension to an existing gas tolling agreement, increasing it to 600 MW beginning in 2027 and extending the term to 2038 and is currently negotiating additional agreements. The scope of projects being negotiated out of the 2024 ASRFP reflects both the expanse of the 2023 ASRFP and the reality of adjusting to tariffs and changing federal policy.
In its most recent ASRFP, issued on November 19, 2025, APS is seeking at least 1,000 MW of resources that can reach commercial operation between 2029 and 2031, but APS will also consider projects that can achieve commercial operation earlier or later.
APS has an aspirational goal to be carbon-neutral by 2050. This means that for any GHG emissions still produced by our generation resources as of 2050, we will aim to offset these emissions elsewhere. This goal reflects APS’s interest in new innovation and market transformations that address carbon emissions, while relying on the IRP and ASRFP processes to help determine the path forward.
Our strategy is to create a sustainable energy future for Arizona that delivers shareholder value and shared value by serving our customers with reliable, affordable, and clean energy.
Serving customers with excellence is foundational to APS’s business and remains our core focus as we adapt to evolving customer needs and emerging technology. Recognizing that every employee impacts our customer experience, we continue to provide information, tools, and resources enabling our teams to design, develop, and implement enhancements to improve our customer experience.
APS’s 24/7 call center answers more than 75% of customer calls within 30 seconds, and our mobile platforms enable our more than one million customers to quickly and easily find the information they need when they need it. We seek to provide relevant and valuable options for customers to manage their bill, including through rate plan options, programs that help them save energy and money, and alerts and notifications that help keep them aware of outages, payments, and usage. APS recently introduced a high-bill analyzer tool enabling phone advisors to provide customers with specific, customized guidance based on their actual usage and habits.
APS’s focus remains on its customers and the communities it serves. Accordingly, it is APS’s goal to achieve an industry-leading, best-in-class customer experience. This multi-year objective includes incrementally improving APS’s J.D. Power (“JDP”) residential and business customer satisfaction ratings from the fourth to the top of second quartile for its customers. For 2024, APS ranked at the top of the second quartile for large investor-owned utilities for both business and residential customers, with the residential results being APS’s highest rank and placement since 2016.
In furtherance of a customer-centric culture, APS employees have delivered an enhanced customer experience in recent years through a number of past and ongoing initiatives, such as improving the ease-of-use of APS’s automated phone system, improving the speed of answering customer calls, advancing phone advisor soft skill development through updated training curriculum, and adding 1,100-plus in-person payment locations, as well as introducing new customer payment channels. Recently, APS redesigned its customer bills with the aim of increasing personalization and helping customers better understand their energy use and find ways to save. APS also implemented numerous enhancements to its website, including improving page-loading speeds, adding user-friendly dashboards, and making content more simple, relevant, and useful. APS enhanced other customer touchpoints, such as communications throughout outages and the online outage center in addition to continuing to communicate with customers in their preferred channels about topics that matter most to them, such as reliability, energy-efficiency, financial assistance, the environment, and programs that enable them to design their own personalized energy experience. Finally, APS continues to focus on employee learning, training, tools, and resources to ensure all employees understand their role in APS customers’ experiences.
Additionally, APS has implementedoffers a variety of financialcustomer assistance programsprogram, including up to supporta customers60% strugglingbill to pay their energy bills. Among these assistance programs are discountsdiscount for qualified limited-incomevulnerable customers, including a new tier with larger discounts for APS’s lowest income customers added in the second quarter of 2024 and other non-income-based assistance programs, such as flexible payment arrangementsarrangements, and emergency utility bill assistance. To ensure ourcustomers mostin vulnerable customersneed are connected to these programs, we train and partner with more thannearly one hundred community action agencies across our service territory.territory to train representatives who serve our shared customers.
While our energy mix evolves, APS’s commitment to deliver reliable service to our customers remains. APS is managing through significant growth in the Phoenix metropolitan area while experiencing supply chain issues similar to those experienced in other industries.
Planned investments will support operating and maintaining the grid, updating technology, accommodating customer growth, and enabling more renewable energy resources. To prioritize reliability and meet substantial growth in customer energy needs, APS has developed a future-focused, strategic transmission plan (the “Ten-Year Transmission Plan”). The Ten-Year Transmission Plan includes five critical transmission projects that comprise the APS strategic transmission portfolio, which represent a significant upgrade to our transmission system. These five projects, along with other projects included in the Ten-Year Transmission Plan, will support growing energy needs, strengthen reliability, and allow for the connection of new resources.
Our advanced distribution management system allows operators to locate outages and control line devices remotely and helps them coordinate more closely with field crews to safely maintain an increasingly dynamic grid. The system will also integrate a new meter data management system that will increase grid visibility and give customers access to more of their energy usage data.
Wildfire safety remains a critical focus for APS and other utilities. We have increased investment in fire mitigation efforts to clear defensible space around our infrastructure, continue ongoing system upgrades, build partnerships with government entities and first responders and educate customers and communities. We also increased spend on mitigating the risk associated with trees that could cause hazards, resulting in more of these trees being removed before they could cause outages or wildfires. These programs contribute to customer reliability, responsible forest management and safe communities. With recent wildfire events in Hawaii, California, and across North America, we have been devoting and will continue to devote substantial efforts to analyzing and developing enhancements to our systems and processes to mitigate fire risk within our service territory and communities, including by hardening our infrastructure, deploying new technologies where appropriate, increasing our awareness, implementing operational changes, and enhancing our wildfire response capabilities. APS completed implementation of fire modelling software that we are utilizing to more surgically identify and calculate risk and target future system improvement investments such as fire-resistant pole wrapping, wood to steel pole conversions, and additional remote-controllable field devices like reclosers and switches. In 2024, APS began installing a system of artificial intelligence-based fire sensing cameras with the ability to detect and alert on fire ignitions. These alerts are sent both to APS and fire response dispatch centers to speed fire response in APS’s service territory regardless of the cause of the fire. APS also implemented a PSPS program on certain feeders that began in the 2024 fire season, leveraging the additional real-time analysis provided by the new modelling software, and has educated and is continuing education outreach to customers and communities that may potentially be impacted by the PSPS program. APS continues to evaluate policy and regulatory options, as well as insurance programs, to mitigate the impact of wildfire events.
For example, on August 14, 2024, APS filed a request with the ACC for a deferral order that would authorize APS to defer, for future recovery in rates, operations and maintenance expenses associated with wildfire management, including increased insurance costs. APS cannot predict the outcome of this matter. See Note 3 for more information.
Additionally, APS was selected by the DOE’s Grid Deployment Office (“GDO”) to receive up to $70 million in federal money for fire mitigation and grid infrastructure projects. This funding is part of the GDO’s Grid Resilience and Innovation Partnership Program and is contingent on APS negotiating and executing final grant agreements with GDO.
Maintaining reliability and affordability for customers during the clean energy transition is fundamental to APS’s strategy. Dispatchable natural gas generators provide energy during times when intermittent resources, such as solar and wind, are insufficient to meet customer demand. In addition to the previously added natural gas units at the modernized Ocotillo Power Plant in 2019 and efficiency improvements to gas units at the Redhawk, Sundance, and West Phoenix Power Plants in 2024, APS has contracted for two simple cycle combustion turbines (approximately 90 MW in total) at Sundance, which are expected to be in service in 2026, and eight simple cycle combustion turbines (approximately 397 MW in total) at Redhawk, which are expected to be in service in 2028. APS continues to evaluate and pursue options for reliably serving growing customer energy needs and demand.
In October 2021, APS announced plans to evaluate regional market solutions as part of the Western Markets Exploratory Group (“WMEG”). As a member of WMEG, APS explored the potential for a staged approach to new market services, including day-ahead energy sales, transmission system expansion, and other power supply and grid solutions consistent with existing regulations and known and expected market design. APS utilizes the work done by WMEG to help identify market solutions that can help achieve carbon reduction goals while supporting reliable, affordable service for customers.
APS went live with a new Energy Management System (“EMS”) in April 2024. APS expects the new EMS to provide a better foundation which will improve future integration of the renewable and energy storage assets into APS’s generation resource portfolio, allowing APS to maximize the flexibility of its resources and fully engage in the Western Energy Imbalance Market (“WEIM”). APS also believes it will better position APS to participate in market opportunities that develop over the next decade.
APS’s key elements to delivering reliable power include resource and transmission planning, sufficient reserve margins, partnering with customers to manage peak demand, fire mitigation, and operational preparedness, among others. Seasonal readiness procedures at APS include inspections to ensure good material conditions and critical control system surveys. APS also plans for the unexpected by conducting emergency operations drills and coordinating with federal, state, and local agencies on fire and emergency management.
APS continues to focus on mitigating the cost pressures related to inflation and other factors, such as tariffs. Overall inflation grew by 1.6% in Phoenix and 2.9% nationally over the twelve months ended December 2024. Although inflationary impacts to APS began to slow in 2024, APS is still managing the impacts high inflation. Additionally, the implementation of recent and future tariffs could further escalate costs and introduce supply chain constraints.
APS’s customer affordability initiative includes internal opportunities, such as training and mentoring employees on identifying efficiency opportunities; maintaining an inventory to take advantage of lower pricing and avoid expediting fees; entering into long-term contracts to hedge against price volatility, which has allowed APS to mitigate against procurement spend areas such as transformers; and implementing automation technologies to enhance efficiencies and increase data-oriented decision making.
There are also external opportunities under APS’s customer affordability initiative, such as APS’s participation in the WEIM. WEIM continues to be a tool for creating savings for APS’s customers from the real-time, voluntary market. APS continues to expect that its participation in WEIM will lower its fuel and purchased-power costs, improve situational awareness for system operations in the Western Interconnection power grid, and improve integration of APS’s renewable resources. APS participated in market design and tariff development of Markets+, a day-ahead and real-time market offering from Southwest Power Pool (“SPP”). The Markets+ tariff was filed with FERC on March 29, 2024 and was approved on January 16, 2025. APS announced a market decision to pursue participation in SPP Markets+. In addition, APS is participating in the Western Resource Adequacy Program administered by Western Power Pool and is transitioning to full binding participation as early as summer 2027. These regional efforts are driven by the objectives of reducing customer cost and improving reliability.
In terms of generation affordability, every three years, APS performs a comprehensive study, called an Integrated Resource Plan (“IRP”), to identify what resources will be necessary to safely and reliably meet the demand and energy needs of its customers over the next 15 years. In November 2023, APS released its latest IRP, which identified forecasted customer demand and energy needs growing at an unprecedented rate. In developing the IRP, APS considered how factors such as forecasted economic growth, impacts from weather, and new resource technology availability impact the amount and type of resources required to reliably meet customer needs. These factors, among others, were used to develop a plan that identified a balanced mix of diverse energy generating resources to reliably serve customers’ future energy needs in the most affordable and sustainable manner possible. To help ensure competitive costs for resources procured by APS, APS regularly issues competitive bid solicitations through the ASRFP process, with the most recent ASRFPs being issued in 2022, 2023, and 2024. These ASRFPs are open to bids for all resource types, including customer-scale (behind the meter) and utility-scale (in front of the meter) resources. Through the ASRFP process, APS has found that clean resources like wind, solar, and energy storage technology, are important elements of a least cost portfolio. During the clean energy transition, dispatchable resources will play a vital role in maintaining grid reliability by serving as a back-up to intermittent energy resources when output is insufficient to meet customer needs. Over the long term, each resource in a balanced and diverse portfolio is expected to provide complementary value and contribute to sustained delivery of reliable electric service.
In addition to managing the cost of electricity generation, APS has continued building upon existing cost management efforts, including a customer affordability initiative launched in 2019. The initiative was implemented company-wide to thoughtfully and deliberately assess our business processes and organizational approaches to completing high-value work and achieving internal efficiencies. APS continues to drive this initiative by identifying opportunities to streamline its business processes, mitigate cost increases, increase employee retention, and improve customer satisfaction.
Clean Energy Commitment
We are committed to doing our part to build a clean and carbon-free future. As Arizona stewards, we do what is right for the people and prosperity of Arizona. Our vision is to create a sustainable energy future for Arizona by providing reliable, affordable, and clean energy to our customers. We can accomplish our vision by collaborating with customers, communities, employees, policymakers, shareholders, and other stakeholders. Our clean energy commitment is based on sound science and supports continued growth and economic development while maintaining reliability and affordable prices for APS’s customers.
APS’s clean energy commitment consists of three parts:
•A 2050 goal to provide 100% clean, carbon-free electricity;
•A 2030 target to achieve a resource mix that is 65% clean energy, with 45% of the generation portfolio coming from renewable energy; and
•A plan to exit from coal-fired generation by 2031.
APS’s ability to successfully execute its clean energy commitment depends upon a number of important external factors, including a supportive regulatory environment, sales and customer growth, development of clean energy technologies, and continued access to capital markets, among others.
2050 Goal: 100% Clean, Carbon-Free Electricity. Achieving a fully clean, carbon-free energy mix by 2050 is our aspiration. Achieving this 2050 goal will require, among other things, innovative thinking, emergent clean energy and storage technologies, upgrades and expansions to the grid, and supportive public policy.
2030 Goal: 65% Clean Energy. APS has an energy mix that is already more than 50% clean and plans to continue to add more renewables and energy storage. By building on those plans, APS intends to attain an energy mix that is 65% clean by 2030, with 45% of APS’s generation portfolio coming from renewable energy. “Clean” is measured as percent of energy mix, which includes all carbon-free resources like nuclear, renewables, and demand-side management. “Renewable” energy includes generation resources such as solar, wind, and biomass, and is measured in accordance with the ACC Renewable Energy Standard as a percentage of retail sales. This target will serve as a checkpoint for our resource planning, investment strategy, and customer affordability efforts as APS moves toward a 100% clean, carbon-free energy mix by 2050.
2031 Goal: Exit Coal-Fired Generation. The plan to exit coal-fired generation by 2031 will require APS to stop relying on coal-generation at Four Corners. APS has permanently retired more than 1,000 MW of coal-fired electric generating capacity. These closures and other measures taken by APS have resulted in annual carbon emissions that were 36% lower in 2023 compared to 2005. In addition, APS has committed to end the use of coal at its remaining Cholla units during 2025.
In June 2021, APS and the owners of Four Corners entered into an agreement that would allow Four Corners to operate seasonally at the election of the owners as early as fall 2023, subject to the necessary governmental approvals and conditions associated with changes in plant ownership. Under seasonal operation, one generating unit would be shut down during seasons where electricity demand is reduced, such as the winter and spring. The other unit would remain online year-round, subject to market conditions as well as planned maintenance outages and unplanned outages. As of the date of this report, APS has elected not to begin seasonal operation due to market conditions.
Renewables. APS’s IRP identifies a diverse mix of resources adequate to maintain grid reliability while serving increasing future customer energy needs. Our IRP shows that renewable and clean resources are an important part of a reliable, cost effective portfolio. APS seeks market-based pricing of procured resources through regular solicitation of project bids using its competitive ASRFP process.
APS has a diverse portfolio of existing and planned resources, including solar, wind, energy storage, nuclear, geothermal, biomass and biogas, that supports our commitment to clean energy. This commitment is already strengthened by Palo Verde, one of the nation’s largest carbon-free, clean energy resources, which provides the foundation for reliable and affordable service for APS customers. APS’s longer-term clean energy strategy includes pursuing the right mix of purchased power contracts for new resources, procurement of new resources to be owned by APS, and the ongoing development of distributed energy resources. Maintaining a balanced and diverse portfolio of resources will ensure continued reliable service to our customers in the most affordable manner possible.
APS uses competitive ASRFPs to pursue market-priced resources that meet its system needs and offer the best value for customers. APS selects projects based on cost, ability to meet system requirements and commercial viability, taking into consideration timing and likelihood of successful contracting and development. Under current market conditions, APS must aggressively contract for resources that can withstand supply chain and other geopolitical pressures. Guided by IRP-established timelines and quantities, APS maintains a flexible approach that allows it to optimize system reliability and customer affordability through the ASRFP process. Agreements for the development and completion of future resources are subject to various conditions, including successful siting, permitting and interconnection to the electric grid.
On June 30, 2023, APS issued an ASRFP (the “2023 ASRFP”) pursuant to which APS procured nearly 7,300 MW of new resources to be in service from 2026 to 2028.
On November 20, 2024, APS issued an ASRFP (the “2024 ASRFP”) seeking 2,000 MW of resources. APS is seeking projects that can reach commercial operation beginning June 1, 2028 through June 1, 2030 but will consider projects that may achieve commercial operation as early as 2026. Additionally, APS is interested in projects that require longer planning, permitting, and construction and can be commercially operational after June 1, 2030. Bids for the 2024 ASRFP were due on February 5, 2025.
The following table summarizes the resources in APS’s renewable energy portfolio that are in operation, planned or under development as of the date of this report. Agreements for the development and completion of future resources are subject to various conditions, including successful siting, permitting, and interconnection of the projects to the electric grid.
(a) Includes rooftop solar facilities owned by third parties. DG is produced in direct current and is converted to alternating current for reporting purposes.
What changed in the latest 10-Q
Risk Factors
In addition to the other information set forth in this report, you should carefully consider the factors discussed in Part I, Item 1A — Risk Factors in the 2025 Form 10-K, which could materially affect the business, financial condition, cash flows or future results of Pinnacle West and APS. The risks described in the 2025 Form 10-K are not the only risks facing Pinnacle West and APS. Additional risks and uncertainties not currently known to us or that we currently deem to be immaterial also may materially adversely affect the business, financial condition, cash flows and/or operating results of Pinnacle West and APS.
No wording changes found in this section.
Full comparison: every changed paragraph (0)
Management's Discussion & Analysis (MD&A)
New heading “Operating Results – Six-month period ended June 30, 2026, compared with six-month period ended June 30, 2025.”
Largest changes
“Operating Results – Six-month period ended June 30, 2026, compared with six-month period ended June 30, 2025.”see in full comparison
“(a) Operating revenues less fuel and purchased power is a non-GAAP financial measure. As reconciled in the table above, this amount is derived by the difference between the GAAP financial statement line item Operating revenues less the GAAP financial statement line item Fuel and purchased power as presented on the Condensed Consolidated Statements of Income. Operating revenues, less fuel and purchased power is used by Pinnacle West to assess whether customer revenues adequately cover fuel and purchased power costs. …”see in full comparison
On January 5, 2023, the ACC opened a new docket to explore the possibility of modifications to the ACC’s historical test year rules. The ACC requested comments and held two workshops exploring ways to reduce regulatory lag, including alternative ratemaking structures such as future test years, hybrid test years, and formula rates. On December 3, 2024, the ACC approved a policy statement regarding formula rate plans. The policy statement provides regulated utilities with the opportunity to propose formula rate plans in future rate cases. On March 28, 2025, RUCO, the ALCG, and an individual customer filed a lawsuit challenging the ACC’s authority to issue the formula rate policy statement outside of Arizona’s formula rulemaking process. On June 13, 2025, the lawsuit challenging the ACC’s formula rate policy was dismissed by the Superior Court of Maricopa County. Following the dismissal, the plaintiffs filed an appeal with the Arizona Court of Appeals as well as a Petition for Special Action with the Arizona Supreme Court. The Supreme Court declined to exercise jurisdiction on the Petition for Special Action. The plaintiffs also filed a Petition for Special Action with the Arizona Court of Appeals, which has accepted jurisdiction to determine whether the case should be remanded back to the Superior Court for expedited consideration of the merits. On November 21, 2025, the Arizona Court of Appeals ruled that the issue should be remanded back to the Superior Court to determine whether the ACC’s formula rate policy must go through a formal rulemaking process. In response, APS, the ACC, and several other Arizona utility companies filed petitions for review of the Court of Appeals decision with the Arizona Supremesee in full comparisonCourt,Court. That petition was denied on May 8, 2026, whichiswillpendingreturnatthethislitigationtime.to the Superior Court of Maricopa County for further proceedings on the merits of whether the ACC’s issuance of the formula rate policy statement complied with the Arizona Administrative Procedure Act. APS cannot predict the outcome of thismatter.matter or the impact (if any) it may have on other proceedings.
Artificial Intelligence. To address the rapid advancement of AI technology risks and opportunities, APS has developed an AI strategy to responsibly utilize AI to advance our business strategy, enhance customer and employee experiences, and optimize operational reliability. At the core of our AI strategy is a focus on cultural transformation and workplace adoption of AI skills, supported by a robust governance model thatsee in full comparisondevelopsguidesguidance,thepolicies,development of policies andrelevant sub-strategiesstrategies for the execution of AI projects at the Company. To ensure compliance with data security, reliability requirements, and our Code of Ethical Conduct, governance and oversight are provided by leadership and experts from our information technology, cybersecurity, human resources, ethics, supply chain, legal, and nuclear generation teams.
Retail electricity sales in kWh, adjusted to exclude the effects of weather variations, increasedsee in full comparison9.4%3.9% for residential customers, 13.6% for commercial and industrial customers, 3.9% for residential customers, and 9.5% for all retail customers for the period endedMarchJune31,30, 2026 compared with the prior-year period. While strong sales to commercial and industrial customers continue to be driven by the ramp-up of new data center and large manufacturing customers, the main drivers of increased revenues for this period were a surge in residential usage during April and May, including on days with normal weather conditions, following strong weather-driven demand caused by a record-setting March heat wave in Arizona in the first quarter of 2026 and steady customergrowthgrowth, which wassomewhatonly partially offset bylower usage among residential customers,energy savings driven by customer conservation, energy efficiency, and distributed renewablegenerationgeneration.initiatives, the main drivers of increased revenues for this period were continued strong salesDue tocommercial and industrial customers and the continued ramp-up of new data center and large manufacturing customers. On account ofthe growth of large load customers as a proportion of our business, in the first quarter of 2025, we updated our procedures with respect to estimates of unbilled revenues. This resulted in a downward adjustment to unbilled revenues in that quarter, which contributes approximately2.0%0.9% to 2026 year-to-date sales growth as compared to the same period last year.
“Our consolidated net income attributable to common shareholders for the six months ended June 30, 2026 was $211 million, compared with consolidated net income attributable to common shareholders of $188 million for the prior-year period. The results reflect an increase of approximately $23 million, primarily as a result of the effects of weather, increased usage and customer growth, lower operations and maintenance expenses, and higher transmission service revenues. Customer growth in turn was partially offset by the related pricing and the impacts of energy efficiency. …”see in full comparison
Full comparison: every changed paragraph (65)
AdditionalCurrently, additional natural gas capacity is necessary to support reliable service and meet increasing energy needs. However, at this time existing natural gas pipelines into Arizona are currentlyfully committed. As a result, in July 2025, APS executed a gas transportation precedent agreement to secure a long-term supply of additional natural gas.gas transportation. The new pipeline is expected to be operational by late 2029 and will be owned and operated by a third-party.third party. In July 2026, APS announced plans to convert two units at Cholla to natural gas, adding approximately 380 MW of gas-fired generation. The plan is subject to change pending the comparison to other generation sources that APS is considering in its evaluation of the 2025 ASRFP. The plan contemplates that construction on the gas conversion would begin in 2028 with a targeted in-service date in 2029. In addition to the planned Cholla gas conversion, APS plans to add up to 2,000 MW of flexible natural gas generation to its portfolio, designed to help meet the growing around-the-clock energy needs in Arizona. APS continues to explore additional development opportunities to meet Arizona’s growing needs.
APS uses fire modeling software to identify and calculate risk and target future system improvement investments such as fire-resistant pole wrapping, wood to steel pole conversions, and additional remote-controllable field devices like reclosers and switches. In 2024, APS began installing a system of artificial intelligence-based fire sensing cameras with the ability to detect and alert on fire ignitions. These alerts are sent both to APS and fire response dispatch centers to speed fire response in APS’s service territory regardless of the cause of the fire. APS also implemented a public safety power shutoff (“PSPS”) program on certain feeders that began in the 2024 fire season, leveraging the additional real-time analysis of weather and environmental factors, such as temperature, humidity, fuel moisture levels, and wind, provided by APS field sensors and the modeling software. APS has educated and will continue education outreach to customers and communities that may potentially be impacted by the PSPS program.
APS was selected by DOE’s Grid Deployment Office (“GDO”) to receive up to $70 million in federal money for fire mitigation and grid infrastructure projects. This funding is part of the GDO’s Grid Resilience and Innovation Partnership Program and is contingent on APS negotiating and executing final grant agreements with GDO. Additionally, on May 12, 2025, the Arizona Governor Hobbsgovernor signed into law a bill that requires Arizona electric utilities to develop and seek approval for wildfire mitigation plans and defines the standard of care with respect to wildfire-related claims by reference to such plans. Pursuant to that legislation, APS has submitted its Comprehensive Wildfire Mitigation Plan to the Arizona Department of Forestry and Fire Management for review and approval. APSThe anticipateswildfire thatmitigation processplan willwas concludeapproved sometimeon inMay the7, second quarter of 2026; however, APS cannot predict the outcome of this matter.2026. APS continues to evaluate policy and regulatory options, as well as insurance programs, to mitigate the impact of wildfire events.
We are committed to keeping bills as low as possible for our customers while maintaining high levels of reliability. Inflation has dramatically impacted the cost of goods and services in recent yearsyears, as shown by the Consumer Price Index for All Urban Consumers (“CPI-U”), which from 2018 through 2024 rose nationally 24.9% and 32.1% in Phoenix. Despite this, APS’s average residential rates remained well-below those inflation figures, rising 16.2% for the same period according to the U.S. Energy Information Administration. Inflation has moderatedrecently fromreached earlierits highs,highest level since 2023, with CPI-U rising 2.4%4.2% nationally in the 12 months ended May 2026 and 1.7%3.0% in Phoenix over the 12 months ended FebruaryApril 2026. As a result of increased tariffs and supply chain constraints, APS amended several of its agreements from its ASRFP issued in 2023 to mitigate these cost impacts. However, APS remains cautious of potential price increases as a result of the ongoing Iraniangeopolitical conflictevents and current and proposed tariffs, which could lead to higher costs and supply chain constraints, while also continuing to monitor the outcomeimpact of the U.S. Supreme Court’s recent decision regarding the validity of certain tariffs and any other related executive or legislative action.
There are also external opportunities that allow APS to deliver more affordable energy to customers, such as APS’s participation in western energy markets and programs. APS participated in market design and tariff development of Markets+, a day-ahead and real-time market offering from the Southwest Power Pool. The Markets+ tariff was filed with FERC on March 29, 2024 and was approved on January 16, 2025. APS is a funding party to the implementation phase of Markets+ and expects to go live in the market in Octoberlate 2027.2027 or early 2028. In addition, APS is participating in the Western Resource Adequacy Program administered by Western Power Pool and plans to transition to full-binding participation in 2027. These regional efforts are driven by the objectives of reducing customer cost and improving reliability. Until the transition to Markets+, APS will continue to participate in the Western Energy Imbalance Market (“WEIM”) as a tool for creating savings for APS’s customers from the real-time only, voluntary market.market for as long as feasible leading up to the transition to Markets+. APS expects that its participation in the WEIM and future participation in Markets+ will lower its fuel and purchased-power costs, improve situational awareness for systems operations in the Western Interconnection, and improve integration of APS’s resources.
APS remains focused on providing reliable energy at the lowest cost possible while striving to lower emissions over time and continues to look for opportunities to support reliability through traditional dispatchable resources, such as gas and the potential extension of coal beyond 2031. APS’s diverse portfolio of existing and planned resources includes biomass, biogas, coal, energy storage, geothermal, natural gas, nuclear, solar, and wind. Every three years, APS performs an IRP, a comprehensive study to identify what resources will be necessary to safely, reliably, and affordably meet the demand and energy needs of its customers over the next 15 years. In November 2023, APS released its latest IRP, which identified forecasted customer demand and energy needs growing at an unprecedented rate. In developing the IRP, APS considered how factors such as forecasted economic growth, impacts from weather, and new resource technology availability impact the amount and type of resources required to reliably and affordably meet customer needs. These factors, among others, were used to develop a plan that identified a balanced mix of diverse energy-generating resources to reliably serve customers’ future energy needs. APS expects to file its next IRP lateron inOctober 30, 2026, which will provide an updated view on the resource types and volumes necessary to maintain reliability for a rapidly expanding customer base. To help ensure competitive costs for resources procured by APS, APS regularly issues competitive bid solicitations through the ASRFP process, with the most recent ASRFP being issued in 2025. These ASRFPs are open to bids for all resource types, including customer-scale (behind the meter) and utility-scale (in front of the meter) resources.
APS has an aspirational goal to be carbon-neutral by 2050. This means that for any GHG emissions still produced by our generation resources as of 2050, we will aim to offset these emissions elsewhere. This goal reflects APS’s interest in new generation and energy storage innovation and market transformations that address carbon emissions, while relying on the IRP and ASRFP processes to help determine the path forward.
APS’s 24/7 call center answers more than 75% of customer calls within 30 seconds, and our mobile platforms enable our more than one million customers to quickly and easily find the information they need when they need it. We seek to provide relevant and valuable options for customers to manage their bill, including through rate plan options, programs that help them save energy and money, and alerts and notifications that help keep them aware of outages, payments, and usage. APS recently introducedhas a high-bill analyzer tool enabling phone advisors to provide customers with specific, customized guidance based on their actual usage and habits. For customers experiencing higher-than-expected bills, APS’s high-bill analyzer tool allows phone advisors to provide specific, customized guidance based on a customer's actual energy-use patterns.
Additionally, APS offers a variety of customer assistance program,resources, including income-qualified bill discounts of up to a 60% bill discount for vulnerableeligible customers, flexible payment arrangements,arrangements and emergency utility bill assistance. To ensure customers inare needaware areof and connected to these programs,resources, weAPS partnerpartners with nearly one hundred community action agencies across our service territoryterritory, providing training and support to train representatives who serve our shared customers. Through these partnerships and programs, APS works to ensure assistance is available to customers when they need it most.
New Nuclear Generation. Along with other Arizona electric utilities, APS is exploring additional nuclear generation to provide around-the-clock carbon-free energy to meet rising energy demands in Arizona. APS has been monitoring emerging nuclear technologies, ranging from newer proposed and installed versions of large-scale reactors to small modular nuclear reactors. Small modular nuclear reactors are typically designed to generate 300 MW or less of energy per unit compared to, for example, the 1,400 MW per unit generated at Palo Verde. The Arizona electric utilities have applied for a grant from DOE to beginbegun preliminary exploration of a potential site for additional nuclear energy for Arizona. The grant could support a three-year site selection process and possible preparation of an early site permit application to NRC.
Artificial Intelligence. To address the rapid advancement of AI technology risks and opportunities, APS has developed an AI strategy to responsibly utilize AI to advance our business strategy, enhance customer and employee experiences, and optimize operational reliability. At the core of our AI strategy is a focus on cultural transformation and workplace adoption of AI skills, supported by a robust governance model that developsguides guidance,the policies,development of policies and relevant sub-strategiesstrategies for the execution of AI projects at the Company. To ensure compliance with data security, reliability requirements, and our Code of Ethical Conduct, governance and oversight are provided by leadership and experts from our information technology, cybersecurity, human resources, ethics, supply chain, legal, and nuclear generation teams.
On March 2 and March 18, 2026, the ACC Staff, RUCO, and other intervenors filed their initial written testimony with the ACC. ACC Staff’s testimony includes the following recommendations, among others, depending on the approval of APS’s proposed FRAM, (i) a $525.2 million total base revenue increase, (ii) a 9.55% to 9.80% return on equity, (iii) a 0.20% return on the increment of fair value, and (iv) 12-months12 months of post-test year plant. RUCO’s testimony includes the following recommendations, among others, depending on the approval of APS’s proposed FRAM, (i) a $200.2 to $278.1 million total base revenue increase, (ii) a 9.00% to 9.20% return on equity, (iii) a 0.0% return on the increment of fair value, and (iv) 0 to 12-months12 months of post-test year plant.
On May 1, 2026, ACC Staff, RUCO, and other intervenors filed their surrebuttal testimonies with the ACC. The ACC Staff adjusted their initial recommendation to a $506.5 million total base revenue increase and additional revisions to the Company’s FRAM proposal, including the continued recommendation for an earnings test “deadband” range of +/- 50 basis points.
On May 11, 2026, APS filed its rejoinder testimony addressing the ACC Staff and intervenors’ surrebuttal testimonies. APS’s rejoinder testimony included adjustments to the proposed schedule for the annual FRAM filing and a reduction of the total revenue requirement increase to $691.6 million, representing a revenue requirement increase, net of adjustor transfers, of $608.7 million. All other major provisions from APS’s rebuttal testimony were maintained in its rejoinder testimony.
On May 1, 2026, ACC Staff, RUCO, and other intervenors filed their surrebuttal testimonies with the ACC, which are publicly available on the ACC’s eDocket website. APS is currently evaluating the surrebuttal testimony and plans to file its rejoinder testimony on May 11, 2026.
APS requested that the increase become effective in the second half of 2026. The hearing forconcluded thison rateJuly 7, 2026. After the conclusion of the hearing, the Administrative Law Judge overseeing the hearing issued a procedural order outlining briefing schedules and other next steps in the proceedings. The order noted that the case is currently scheduledanticipated to beginbe inresolved Maybefore 2026.the end of this year. APS cannot predict the outcome of its request nor when the 2025 Rate Case will be decided by the ACC.
Six intervenors and the Attorney General of Arizona requested rehearing on various issues included in the ACC’s decision, such as the GAC for solar customers, the SRB, and Coal Community Transition funding. On April 15, 2024, the ACC granted, in part, the rehearing applications of the Attorney General, AriSEIA, SEIA, and Vote Solar specifically to review whether the GAC rate is just and reasonable, including whether it should be higher or lower, whether the GAC rate constitutes a discriminatory fee to solar customers, and whether omission of a GAC charge is discriminatory to non-solar customers. All other applications for rehearing were denied. A limited rehearing was held October 28 through November 1, 2024. Following the limited rehearing, an Administrative Law Judge issued the Limited Rehearing ROO on December 3, 2024, which recommended affirming the GAC as just and reasonable and that the GAC is not discriminatory to solar customers and the absence of a GAC is not discriminatory to non-solar customers. On December 17, 2024, the ACC approved the Limited Rehearing ROO with an amendment that requires APS in its next rate case to propose a revenue allocation based on a site-load cost of service study in order to bring further parity in revenue collection between solar and non-solar customers. SEIA, AriSEIA, Vote Solar, the Arizona Attorney General, and two individual customers have filed requests for rehearing of the ACC’s December 17, 2024 decision on the rehearing. The ACC has taken no action on these requests. In addition, each of these parties has subsequently filed an appeal to the Arizona Court of Appeals seeking review of the ACC’s decisions regarding the GAC and on rehearing. On February 25, 2026, parties provided oral arguments before the Court of Appeals. On June 16, 2026, the Arizona Court of Appeals found that the GAC and related increases for residential solar customers were imposed by the ACC without adequate notice or opportunity to be heard. APS has since moved for reconsideration of this decision and, if reconsideration is not successful, plans to seek further review of this decision before the Arizona Supreme Court. APS cannot predict the outcome of these proceedings.proceedings, but does not expect the outcome will have a material impact on APS’ financial position, results of operations, or cash flows.
On January 5, 2023, the ACC opened a new docket to explore the possibility of modifications to the ACC’s historical test year rules. The ACC requested comments and held two workshops exploring ways to reduce regulatory lag, including alternative ratemaking structures such as future test years, hybrid test years, and formula rates. On December 3, 2024, the ACC approved a policy statement regarding formula rate plans. The policy statement provides regulated utilities with the opportunity to propose formula rate plans in future rate cases. On March 28, 2025, RUCO, the ALCG, and an individual customer filed a lawsuit challenging the ACC’s authority to issue the formula rate policy statement outside of Arizona’s formula rulemaking process. On June 13, 2025, the lawsuit challenging the ACC’s formula rate policy was dismissed by the Superior Court of Maricopa County. Following the dismissal, the plaintiffs filed an appeal with the Arizona Court of Appeals as well as a Petition for Special Action with the Arizona Supreme Court. The Supreme Court declined to exercise jurisdiction on the Petition for Special Action. The plaintiffs also filed a Petition for Special Action with the Arizona Court of Appeals, which has accepted jurisdiction to determine whether the case should be remanded back to the Superior Court for expedited consideration of the merits. On November 21, 2025, the Arizona Court of Appeals ruled that the issue should be remanded back to the Superior Court to determine whether the ACC’s formula rate policy must go through a formal rulemaking process. In response, APS, the ACC, and several other Arizona utility companies filed petitions for review of the Court of Appeals decision with the Arizona Supreme Court,Court. That petition was denied on May 8, 2026, which iswill pendingreturn atthe thislitigation time.to the Superior Court of Maricopa County for further proceedings on the merits of whether the ACC’s issuance of the formula rate policy statement complied with the Arizona Administrative Procedure Act. APS cannot predict the outcome of this matter.matter or the impact (if any) it may have on other proceedings.
•$25 million investment in the Energy Impact Partners fund, of which approximately $21 million has been funded as of MarchJune 31,30, 2026. Energy Impact Partners is an organization that focuses on fostering innovation and supporting the transformation of the utility industry.
•$25 million investment in Copper Sky, previously AZ-VC, of which approximately $17$19 million has been funded as of MarchJune 31,30, 2026. Copper Sky is a fund focused on analyzing, investing, managing, and otherwise dealing with investments in privately-held early stage and emerging growth technology companies and businesses primarily based in Arizona, or based in other jurisdictions and having existing or potential strategic or economic ties to companies or other interests in Arizona.
•$7.5 million investment in Westly Seed Fund, of which approximately $2 million has been funded as of MarchJune 31,30, 2026. Westly Seed Fund is focused on supporting entrepreneurs involved in the energy, mobility, building, and industrial sectors.
•Equity investment in SAI, a private corporation that manufactures electrical switchgear equipment used by data centers. El Dorado accounts for this investment under the equity method and has an investment carrying value of approximately $26$34 million as of MarchJune 31,30, 2026.
Actual and Projected Customer and Sales Growth. Retail customers in APS’s service territory increased 2.2%2.1% for the period ended MarchJune 31,30, 2026 compared with the prior-year period. For the three years through 2025, APS’s customer growth averaged 2.2% per year. We currently project annual customer growth to be 1.5% to 2.5% for 2026 and the average annual growth to be in the range of 1.5% to 2.5% through 2030 based on anticipated steady population growth in Arizona during that period.
Retail electricity sales in kWh, adjusted to exclude the effects of weather variations, increased 9.4%3.9% for residential customers, 13.6% for commercial and industrial customers, 3.9% for residential customers, and 9.5% for all retail customers for the period ended MarchJune 31,30, 2026 compared with the prior-year period. While strong sales to commercial and industrial customers continue to be driven by the ramp-up of new data center and large manufacturing customers, the main drivers of increased revenues for this period were a surge in residential usage during April and May, including on days with normal weather conditions, following strong weather-driven demand caused by a record-setting March heat wave in Arizona in the first quarter of 2026 and steady customer growthgrowth, which was somewhatonly partially offset by lower usage among residential customers, energy savings driven by customer conservation, energy efficiency, and distributed renewable generationgeneration. initiatives, the main drivers of increased revenues for this period were continued strong salesDue to commercial and industrial customers and the continued ramp-up of new data center and large manufacturing customers. On account of the growth of large load customers as a proportion of our business, in the first quarter of 2025, we updated our procedures with respect to estimates of unbilled revenues. This resulted in a downward adjustment to unbilled revenues in that quarter, which contributes approximately 2.0%0.9% to 2026 year-to-date sales growth as compared to the same period last year.
For the three years through 2025, annual retail electricity sales growth averaged 3.9%, adjusted to exclude the effects of weather variations. Due to the expected growth of several data centers and large manufacturing facilities, we currently project that annual retail electricity sales in kWh will increase in the range of 4.0% to 6.0% for 2026 and that average annual growth will be in the range of 5.0% to 7.0% through 2030, including the effects of customer conservation, energy efficiency, and distributed renewable generation initiatives,generation, but excluding the effects of weather variations. These projected sales growth ranges include the impacts of several data centers and large manufacturing facilities, which are expected to contribute to 2026 growth in the range of 3.0% to 5.0% and to average annual growth in the range of 4.0% to 6.0% through 2030.
Operating Results – Three-month period ended MarchJune 31,30, 2026, compared with three-month period ended MarchJune 31,30, 2025.
Our consolidated net income attributable to common shareholders for the three months ended MarchJune 31,30, 2026 was $33$179 million, compared with consolidated net lossincome attributable to common shareholders of $5$193 million for the prior-year period. The results reflect ana increasedecrease of approximately $38$14 million, primarily as a result of higher transmission revenues, lower operations and maintenance expenses, the effects of weather, due primarily to extreme heat during February and March, the hottest on record in APS’s service territory, and customer usage, growth and related pricing. These positive factors were partially offset by higher interest charges, lower other income due to El Dorado investment gains recognized in the prior year, higher income taxes due to higher pre-tax income, partially offset by higher tax credits, and higher depreciation and amortization expenses mostly due to increased plant additions and intangible assets,additions, partially offset by operations ceasing at ChollaCholla, and lower transmission service revenues. These negative factors were partially offset by the favorable impacts of the effects of weather, increased customer usage, customer growth, lower operations and maintenance expenses, and lower income taxes. Customer growth in 2025.turn was partially offset by the related pricing and the impacts of energy efficiency.
Operating revenues less fuel and purchased power. Operating revenues less fuel and purchased power expenses were $61$16 million higher for the three months ended MarchJune 31,30, 2026 compared with the prior-year period. The following table summarizes the major components of this change (dollars in millions):
Operations and maintenance. Operations and maintenance expenses decreased $23$4 million for the three months ended MarchJune 31,30, 2026 compared with the prior-year period,period primarily due to:
Depreciation and amortization. Depreciation and amortization expenses were $5$14 million higher for the three months ended MarchJune 31,30, 2026 compared to the prior-year period, primarily due to increased plant additionsin and intangible assets,service, partially offset by operations ceasing at the Cholla in 2025.plant.
Other income and expense, net. Other income and expense, net was $15$5 million lower for the three months ended MarchJune 31,30, 2026 compared to the prior-year period, primarily due to lower PSA interest income and higher other expenses, partially offset by investment gains in El Dorado recognized in the prior year and lower PSA interest income.Captive. The difference between APS’s and Pinnacle West’s other income and expense, net is primarily related to Pinnacle West’s gaininvestment gains in investmentthe in El Dorado.Captive.
Interest charges, net of allowance for borrowed funds and equity funds used during construction. Interest charges, net of allowance for funds used during construction, were $19$18 million higher for the three months ended MarchJune 31,30, 2026 compared to the prior-year period, primarily due to higher debt balances.balances, partially offset by higher allowance for equity funds used during construction.
IncomeTaxes other than income taxes. IncomeTaxes other than income taxes were $7$4 million higher for the three months ended MarchJune 31,30, 20262026, compared withto the prior-year period, primarily due to higher pre-taxplant income, partially offset by higher tax credits.balances.
Income taxes. Income taxes were $4 million lower for the three months ended June 30, 2026 compared with the prior-year period, primarily due to lower pre-tax income.
Operating Results – Six-month period ended June 30, 2026, compared with six-month period ended June 30, 2025.
Our consolidated net income attributable to common shareholders for the six months ended June 30, 2026 was $211 million, compared with consolidated net income attributable to common shareholders of $188 million for the prior-year period. The results reflect an increase of approximately $23 million, primarily as a result of the effects of weather, increased usage and customer growth, lower operations and maintenance expenses, and higher transmission service revenues. Customer growth in turn was partially offset by the related pricing and the impacts of energy efficiency. These positive factors were partially offset by higher interest charges, lower other income mainly due to higher El Dorado other income recognized in the prior year, and higher depreciation and amortization expenses mostly due to increased plant additions and intangible assets, partially offset by operations ceasing at Cholla.
The following table presents net income attributable to common shareholders compared with the prior year for Pinnacle West consolidated and for APS consolidated (dollars in millions):
(a) Operating revenues less fuel and purchased power is a non-GAAP financial measure. As reconciled in the table above, this amount is derived by the difference between the GAAP financial statement line item Operating revenues less the GAAP financial statement line item Fuel and purchased power as presented on the Condensed Consolidated Statements of Income. Operating revenues, less fuel and purchased power is used by Pinnacle West to assess whether customer revenues adequately cover fuel and purchased power costs. This metric is not defined by GAAP and may differ from similar measures used by other companies. This measure is not a substitute for operating income under GAAP.
Operating revenues less fuel and purchased power. Operating revenues less fuel and purchased power expenses were $76 million higher for the six months ended June 30, 2026 compared with the prior-year period. The following table summarizes the major components of this change (dollars in millions):
Operations and maintenance. Operations and maintenance expenses decreased $27 million for the six months ended June 30, 2026 compared with the prior-year period, primarily due to:
Depreciation and amortization. Depreciation and amortization expenses were $19 million higher for the six months ended June 30, 2026 compared to the prior-year period, primarily due to increased plant in service and intangible assets, partially offset by lower depreciation expense due to operations ceasing at the Cholla plant.
Other income and expense, net. Other income and expense, net was $21 million lower for the six months ended June 30, 2026 compared to the prior-year period, primarily due to lower other income from El Dorado, lower PSA interest income and higher other expenses. The difference between APS’s and Pinnacle West’s other income and expense, net is primarily related to Pinnacle West’s other income from El Dorado.
Interest charges, net of allowance for borrowed funds and equity funds used during construction. Interest charges, net of allowance for funds used during construction, were $37 million higher for the six months ended June 30, 2026 compared to the prior-year period, primarily due to higher debt balances, partially offset by higher allowance for equity funds used during construction.
Taxes other than income taxes. Taxes other than income taxes for the for the six months ended June 30, 2026 were $7 million higher, compared to the prior-year period, primarily due to higher plant balances.
Income taxes. Income taxes were $3 million higher for the six months ended June 30, 2026 compared with the prior-year period, primarily due to higher pre-tax income, partially offset by higher tax credits.
Our primary sources of cash are dividends from APS and external debt and equity issuances. An ACC order does not allow APS to pay common dividends if the payment would reduce its common equity ratio below 40%. Per the related ACC order, the common equity ratio is defined as total shareholder equity divided by the sum of total shareholder equity and long-term debt, including current maturities of long-term debt. As of MarchJune 31,30, 2026, APS’s common equity ratio, as defined, was 50%.51%. APS’s total shareholder equity was approximately $8.9$9.0 billion, and total capitalization, as calculated pursuant to the ACC order, was approximately $17.7$17.8 billion. Under this order, APS would be prohibited from paying dividends if such payment would reduce its total shareholder equity below approximately $7.1 billion, assuming APS’s total capitalization remains the same. This restriction does not materially affect Pinnacle West’s ability to meet its ongoing cash needs or ability to pay dividends to shareholders.
Dividends to Pinnacle West from APS are also dependent on a number of factors including, among others, APS’s financial condition and free cash flow, the sources of which vary from quarter-to-quarter due in part to the seasonal nature of electricity demand in Arizona. APS’s sources of cash include cash from operations and external sources of liquidity, including long- and short-term external debt financing such as commercial paper, term loans and its revolving credit facility. Cash from operations is dependent upon, among other things, the rates APS may charge and the timeliness of recovering costs incurred through its rates and adjustor recovery mechanisms. Regulatory lag may delay recovery and affect operating cash flows. APS’s capital requirements consist primarily of capital expenditures and maturities of long-term debt. APS funds its capital requirements with cash from operations and, to the extent necessary, external debt financings and equity infusions from Pinnacle West. On December 17, 2024, the ACC issued a financing order approving a limit on yearly equity infusions equal to 2.5% of APS’s total assets each calendar year on a three-year rolling average basis, subject to APS’s equity ratio remaining below the most recently approved rate case capital structure plus 50 basis points. On July 31, 2026, APS submitted an application to the ACC requesting to increase the long-term debt limit from $9.5 billion to $12 billion. APS cannot predict the outcome of this matter.
Pinnacle West has an ATM Program under which Pinnacle West may offer and sell Pinnacle West common stock and enter into forward sale agreements from time to time, subject to market conditions and other factors. Approximately $434 million of common stock is available to be issued under the ATM Program, which takes into account the forward sale agreements in effect as of March 31, 2026. Pinnacle West also has forward sale agreements from an equity offering in February 2024 in effect as of MarchJune 31,30, 2026. See “Financing Cash Flows and Liquidity—Equity Offerings” below and Note 13 for more information.
Three-monthSix-month period ended MarchJune 31,30, 2026 compared with three-monthsix-month period ended MarchJune 31,30, 2025. Pinnacle West’s consolidated net cash provided by operating activities was $235$629 million in 2026 compared to $402$663 million in 2025, a decrease of $167$34 million in net cash provided, primarily due to $74 million higher payments for operations and maintenance costs, $53 million higher working capital, $50$68 million in higher payments for fuel and purchased power costs, $27$35 million in higher interest paid on debtdebt, net of amounts capitalized, and $25$14 million higher payments for other taxes paid; partially offset by $65$61 million higher cash receipts from electric revenues.revenues and $22 million in higher working capital, net. The difference between APS’s and Pinnacle West’s net cash provided by operating activities primarily relates to APS’s lower interest paid on debt, net of amounts capitalized, and other changes in working capital.
Retirement plans and other postretirement benefits. Pinnacle West sponsors a qualified defined benefit pension plan and a non-qualified supplemental excess benefit retirement plan for the employees of Pinnacle West and our subsidiaries. Pinnacle West also sponsors other postretirement benefit plans for the employees of Pinnacle West and its subsidiaries. The requirements of the Employee Retirement Income Security Act of 1974 (“ERISA”) require us to contribute a minimum amount to the qualified plan. We contribute at least the minimum amount required under ERISA regulations, but no more than the maximum tax-deductible amount. Future year contribution amounts are dependent on plan asset performance and plan actuarial assumptions. The expected minimum required cash contributions for the pension plan are zero for the next three yearsyears. andHowever, while we do not expect to make any voluntary cash contributions in 2026, we are evaluating whether to make voluntary contributions in 2027 orand 2028;2028. however,The amounts of voluntary contributions, if any, will be determined as we continue to evaluate and assess our ongoing contribution strategy. Regarding contributions to our other postretirement benefit plan, we have not made a contribution year-to-date in 2026 and do not expect to make any contributions in 2026, 2027 or 2028. We continually monitor financial market volatility and its impact on our retirement plans and other postretirement benefits, but we believe our liability driven investment strategy helps to minimize the impact of market volatility on our plan’s funded status.
Three-monthSix-month period ended MarchJune 31,30, 2026 compared with three-monthsix-month period ended MarchJune 31,30, 2025. Pinnacle West’s consolidated net cash used for investing activities was $551$1,200 million in 2026 compared to $586$1,253 million in 2025, a decrease of $35$53 million of cash used primarily related to a $39$70 million increase in contributions in aid of construction; partially offset by ana $8$25 million increase in capital expenditures. See “Capital Expenditures” below for additional details.
The estimated capital expenditures presented above do not include amounts related to the Cholla gas conversion project, which is currently expected to cost up to approximately $440 million. In addition, projected capital expenditures for entities other than APS are not included, as such amounts are expected to be immaterial.
The table above does not include capital expenditures related to PNW Power projects.
Three-monthSix-month period ended MarchJune 31,30, 2026 compared with three-monthsix-month period ended MarchJune 31,30, 2025. Pinnacle West’s consolidated net cash provided by financing activities was $316$574 million in 2026 compared to $190$605 million in 2025, ana increasedecrease of $126$31 million in net cash provided primarily due to ana increasenet decrease of $595$775 million higherin issuancesshort-term of long-term debtborrowings; partially offset by a $465$450 million decrease in short-termlong-term debt repayments and a $297 million increase in long-term borrowings.
APS’s consolidated net cash provided by financing activities was $503 million in 2026 compared to $561 million in 2025, a decrease of $58 million in net cash provided primarily due to a net decrease of $753 million in short-term borrowings and $200 million in lower equity infusions from the parent; partially offset by a $595 million increase in long-term borrowings and a $300 million decrease in long-term debt repayments.
Significant Financing Activities. On AprilJune 22,24, 2026, the Pinnacle West Board of Directors declared a dividend of $0.91 per share of common stock, payable on JuneSeptember 1, 2026, to shareholders of record on MayAugust 4,3, 2026.
On June 5, 2026, Pinnacle West contributed $100 million into APS in the form of an equity infusion. APS used this contribution to pay down short-term indebtedness consisting of commercial paper.
Equity Offerings. Pinnacle West entered into certain equity forward sale agreements in February 2024 and has an ATM Program under which Pinnacle West may offer and sell Pinnacle West common stock and enter into equity forward sale agreements from time to time, subject to market conditions and other factors. These agreements may be settled at Pinnacle West’s discretion by issuing shares of Pinnacle West common stock and receiving cash, if any, at the then-applicable forward sales price. See Note 13. The following table summarizes the activity relating to these forward sale agreements and the ATM Program as of MarchJune 31,30, 2026 (dollars in thousands, except price per share):
(e) Does not include one forward sale agreement, whose effective date was July 6, 2026, relating to a total of $84 million, on a gross basis, of common stock, with a maturity date of July 3, 2028.
Pinnacle West’s and APS’s debt covenants related to their respective bank financing arrangements include maximum debt to capitalization ratios. Pinnacle West and APS comply with these covenants. For both Pinnacle West and APS, these covenants require that the ratio of consolidated debt to total consolidated capitalization not exceed 65%. As of MarchJune 31,30, 2026, the ratio was approximately 61%62% for Pinnacle West and 51% for APS. Failure to comply with such covenant levels would result in an event of default which, generally speaking, would require the immediate repayment of the debt subject to the covenants and could “cross-default” other debt.
PNW insider buying and selling (Form 4)
Since 2026-04-11, insiders reported open-market purchases in 0 Form 4 filings and open-market sales in 3 filings (3 insiders, 3 trade dates, 9,347 shares, about $930.9K). Net open-market shares: -9,347 (purchases minus sales); net value about -$930.9K.Totals add up every open-market (code P and S) line in those filings, using the prices reported in the filings. Awards, option exercises, tax withholding and gifts are listed below but not counted.
| Trade date | Insider | Transaction | Shares | Price | Value |
|---|---|---|---|---|---|
| 2026-08-10 | Blankenship Elizabeth A |
Open-market sale | 980 | $99.17 | $97.2K |
| 2026-08-07 | Esparza Jose Luis Jr |
Open-market sale | 1,800 | $102.01 | $183.6K |
| 2026-05-14 | Sims Paula J |
Grant/award | 1,665 | $99.77 | $166.1K |
| 2026-05-14 | Spence William H |
Grant/award | 1,665 | $99.77 | $166.1K |
| 2026-05-13 | Tetlow Jacob |
Open-market sale | 6,526 | $99.00 | $646.1K |
| 2026-05-13 | Tetlow Jacob |
Open-market sale | 41 | $99.01 | $4.1K |
Well-known investors holding PNW (13F)
| Investor | Quarter | Shares | Reported value | % of their 13F | Change vs prior quarter |
|---|---|---|---|---|---|
| Two Sigma Investments | 2026-06-30 | 2,517,347 | $269.4M | 0.2% | Added 15% |
| D. E. Shaw & Co. | 2026-06-30 | 0 | $119.9M | 0.07% | No change |
| Citadel Advisors (Ken Griffin) | 2026-06-30 | 0 | $63.3M | 0.04% | No change |
| Gotham Asset Management (Joel Greenblatt) | 2026-06-30 | 474,615 | $50.8M | 0.12% | Reduced 5% |
| Renaissance Technologies | 2026-06-30 | 435,000 | $46.5M | 0.06% | Reduced 24% |
| AQR Capital Management (Cliff Asness) | 2026-06-30 | 432,833 | $46.3M | 0.02% | Added 2% |
| Point72 Asset Management (Steve Cohen) | 2026-06-30 | 365,338 | $39.1M | 0.06% | Added 257% |
| Millennium Management (Israel Englander) | 2026-06-30 | 333,402 | $35.7M | 0.02% | Reduced 24% |
| Point72 Asset Management (Steve Cohen) | 2026-06-30 | 0 | $30.5M | 0.05% | New position |
| Citadel Advisors (Ken Griffin) | 2026-06-30 | 265,831 | $28.4M | 0.02% | Added 459% |
| Bridgewater Associates | 2026-06-30 | 169,107 | $18.1M | 0.07% | Added 3% |
| Two Sigma Investments | 2026-06-30 | 0 | $4.9M | — | Sold out |
| D. E. Shaw & Co. | 2026-06-30 | 26,106 | $2.8M | 0.0% | Added 15% |